Caltrans Logo

Murrieta Hot Springs Road

Description: Murrieta Hot Springs Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City Murrieta
Zip Code 92562
 
Senate District
36
Assembly District 66
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  6519      
Peak Period Time Savings (minutes)      17%-21%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Murrieta Brian Stephenson (951) 304-2489   bstephenson@murrieta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$478 $-143 $335
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$192 $-57 $135
Private***
$0 $0 $0
 
Total**** $670 $-200 $470

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$7 $-5 $2 $0 $0 $2
Design(PS&E)
$66 $-25 $41 $52 $52 $-10
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$597 $-170 $427 $419 $419 $8
 
Total* $670 $-200 $470 $471 $471 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/30/2008 

08/30/2008 
 

 
07/30/2008 

08/30/2008 
100  07/17/2008 

08/19/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

09/30/2008 
10/14/2009 

10/14/2009 
07/17/2008 

04/27/2009 
100  07/17/2008 

04/27/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/30/2008 

05/30/2009 
10/14/2009 

09/22/2010 
08/03/2009 

12/31/2010 
100  08/03/2009 

12/31/2010 


Begin Closeout Phase

End Closeout Phase
09/30/2009 

10/30/2009 
09/22/2010 

 
01/01/2011 

02/28/2011 
100  01/01/2011 

03/03/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 6519
Peak Period Time Savings (minutes) 17%-21%

Bond Funding Cost
Adopted:
$478,000
Current Approved:
$335,387
Actual Expenditures:
$335,388

 

Status as of December 31, 2023.