Countywide TLSP

Description: Countywide TLSP

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange County
City Aliso Viejo, Anaheim, Buena Park, Cypress, Dana Point, Fountain Valley, Fullerton, Garden Grove, Huntington Beach, Irvine, La Habra, La Palma, Laguna Hills, Laguna Niguel, Laguna Woods, Lake Forest, Mission Viejo, Orange, Placentia, Rancho Santa Margarita, Seal Beach, Stanton, Tustin, Westminster, Yorba Linda
Zip Code 90620, 90621, 90623, 90630, 90631, 90638, 90680, 90720, 90740, 92604, 92606, 92618, 92629, 92630, 92637, 92646, 92647, 92648, 92649, 92653, 92655, 92656, 92677, 92683, 92688, 92691, 92692, 92708, 92709, 92780, 92782, 92801, 92802, 92804, 92805, 92806, 92807, 92831, 92832, 92833, 92840, 92841, 92843, 92844, 92845, 92861, 92863, 92867, 92869, 92870, 92886, 92887
 
Senate District
29, 33, 34, 35
Assembly District 56, 60, 67, 68, 69, 70, 71, 72
Congressional District 40, 42, 46, 47, 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      13%  
Peak Delay Time Saving(minutes)  174830      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Orange County Transportation Authority Ronald Keith TSOS (714) 560-5990   rkeith@octa.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$4,000 $-153 $3,847
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$4,000 $0 $4,000
Private***
$0 $0 $0
 
Total**** $8,000 $-153 $7,847

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,000 $-153 $7,847 $7,691 $7,691 $156
 
Total* $8,000 $-153 $7,847 $7,691 $7,691 $156

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/15/2008 

12/01/2008 
 

 
09/15/2008 

12/01/2008 
100  09/15/2008 

12/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/31/2008 

01/31/2009 
 

 
12/31/2008 

01/31/2009 
100  12/31/2008 

01/31/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2009 

01/31/2012 
04/08/2010 

04/08/2010 
07/01/2010 

09/30/2012 
100  07/01/2009 

05/15/2014 
12 

-20 
Begin Closeout Phase

End Closeout Phase
01/31/2012 

01/31/2013 
10/31/2012 

 
12/31/2012 

06/30/2013 
100  07/02/2012 

01/06/2015 


-18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 13%
Peak Delay Time Saving(minutes) 174830

Bond Funding Cost
Adopted:
$4,000,000
Current Approved:
$3,847,000
Actual Expenditures:
$3,845,510

 

Status as of December 31, 2023.