Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Countywide TLSP |
Description: Countywide TLSP
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Aliso Viejo, Anaheim, Buena Park, Cypress, Dana Point, Fountain Valley, Fullerton, Garden Grove, Huntington Beach, Irvine, La Habra, La Palma, Laguna Hills, Laguna Niguel, Laguna Woods, Lake Forest, Mission Viejo, Orange, Placentia, Rancho Santa Margarita, Seal Beach, Stanton, Tustin, Westminster, Yorba Linda |
Zip Code | 90620, 90621, 90623, 90630, 90631, 90638, 90680, 90720, 90740, 92604, 92606, 92618, 92629, 92630, 92637, 92646, 92647, 92648, 92649, 92653, 92655, 92656, 92677, 92683, 92688, 92691, 92692, 92708, 92709, 92780, 92782, 92801, 92802, 92804, 92805, 92806, 92807, 92831, 92832, 92833, 92840, 92841, 92843, 92844, 92845, 92861, 92863, 92867, 92869, 92870, 92886, 92887 |
Senate District |
29, 33, 34, 35 |
Assembly District | 56, 60, 67, 68, 69, 70, 71, 72 |
Congressional District | 40, 42, 46, 47, 48 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 13% | |
Peak Delay Time Saving(minutes) | 174830 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Orange County Transportation Authority | Ronald Keith TSOS | (714) 560-5990 | rkeith@octa.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$4,000 | $-153 | $3,847 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$4,000 | $0 | $4,000 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $8,000 | $-153 | $7,847 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$8,000 | $-153 | $7,847 | $7,691 | $7,691 | $156 | |
Total* | $8,000 | $-153 | $7,847 | $7,691 | $7,691 | $156 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/15/2008 12/01/2008 |
|
09/15/2008 12/01/2008 |
100 | 09/15/2008 12/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/31/2008 01/31/2009 |
|
12/31/2008 01/31/2009 |
100 | 12/31/2008 01/31/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2009 01/31/2012 |
04/08/2010 04/08/2010 |
07/01/2010 09/30/2012 |
100 | 07/01/2009 05/15/2014 |
12 -20 |
Begin Closeout Phase
End Closeout Phase |
01/31/2012 01/31/2013 |
10/31/2012 |
12/31/2012 06/30/2013 |
100 | 07/02/2012 01/06/2015 |
6 -18 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 13% | |
Peak Delay Time Saving(minutes) | 174830 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,000,000 |
Current Approved: |
$3,847,000 |
Actual Expenditures: |
$3,845,510 |
Status as of December 31, 2023.