Description: Folsom Blvd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City Rancho Cordova
Zip Code 95670
 
Senate District
01, 06
Assembly District 10
Congressional District 03, 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0%  
Peak Delay Time Saving(minutes)  4650      
Peak Period Time Savings (minutes)      0  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Rancho Cordova John Samuelson (916) 851-8716   jsamuelson@cityofranchocordova.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$180 $0 $180
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$280 $0 $280
Private***
$0 $0 $0
 
Total**** $460 $0 $460

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$70 $0 $70 $70 $70 $0
Right of Way
$10 $0 $10 $10 $10 $0
Construction
$380 $0 $380 $462 $462 $-82
 
Total* $460 $0 $460 $542 $542 $-82

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/30/2008 

01/06/2009 
 

 
07/30/2008 

01/06/2009 
100  09/30/2008 

01/06/2009 
-2 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2008 

01/30/2009 
 

 
09/30/2008 

01/30/2009 
100  09/30/2008 

01/06/2009 


Begin Right of Way Phase

End Right of Way Phase
01/30/2009 

02/28/2009 
 

 
01/30/2009 

02/28/2009 
100  09/30/2008 

01/06/2009 


Begin Construction Phase

End Construction Phase
03/30/2009 

06/30/2009 
10/21/2009 

10/21/2009 
09/01/2009 

12/09/2009 
100  09/01/2009 

05/28/2010 


-6 
Begin Closeout Phase

End Closeout Phase
07/30/2009 

09/30/2009 
10/21/2009 

 
01/30/2010 

02/27/2010 
100  05/28/2010 

01/13/2011 
-4 

-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0%
Peak Delay Time Saving(minutes) 4650
Peak Period Time Savings (minutes) 0

Bond Funding Cost
Adopted:
$180,000
Current Approved:
$180,000
Actual Expenditures:
$180,000

 

Status as of December 31, 2023.