Description: Foothill Blvd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino County
City Rancho Cucamonga
Zip Code 91701, 91729, 91737, 91739
 
Senate District
31
Assembly District 63
Congressional District 26
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      15%  
Peak Delay Time Saving(minutes)  18240      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Rancho Cucamonga Jason Welday (909) 477-2740   jason.welday@cityofrc.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$225 $0 $225
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$750 $-262 $487
Private***
$0 $0 $0
 
Total**** $974 $-262 $712

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$74 $-37 $37 $37 $37 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$900 $-225 $675 $860 $860 $-185
 
Total* $974 $-262 $712 $898 $898 $-185

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/30/2008 

06/30/2008 
 

 
03/30/2008 

06/30/2008 
100  12/30/2007 

08/30/2008 


-2 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2007 

08/30/2008 
 

 
12/30/2007 

08/30/2008 
100  12/30/2007 

08/30/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  12/30/2007 

08/30/2008 


Begin Construction Phase

End Construction Phase
09/30/2008 

12/30/2008 
10/31/2009 

10/13/2009 
03/26/2009 

12/30/2009 
100  03/26/2009 

12/30/2009 


Begin Closeout Phase

End Closeout Phase
01/30/2009 

01/30/2009 
 

 
01/20/2010 

02/26/2010 
100  01/20/2010 

03/23/2010 


-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 15%
Peak Delay Time Saving(minutes) 18240

Bond Funding Cost
Adopted:
$225,000
Current Approved:
$225,000
Actual Expenditures:
$225,000

 

Status as of December 31, 2023.