East ITS Coordination |
Description: East ITS Coordination
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Placer County |
City | Roseville |
Zip Code | 95661 |
Senate District |
01 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 4214 | |
Peak Period Time Savings (minutes) | 25% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Roseville | Mark Johnson | (916) 774-5410 | mjohnson@roseville.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$1,165 | $-253 | $912 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$129 | $-28 | $101 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,294 | $-281 | $1,013 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,294 | $-281 | $1,013 | $1,014 | $1,014 | $-0 | |
Total* | $1,294 | $-281 | $1,013 | $1,014 | $1,014 | $-0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/30/2008 07/30/2008 |
|
07/30/2008 07/30/2008 |
100 | 06/02/2008 07/23/2008 |
1 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/2008 07/30/2008 |
|
07/30/2008 07/30/2008 |
100 | 07/24/2008 07/31/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/30/2008 12/30/2008 |
07/09/2009 07/09/2009 |
06/01/2009 12/01/2009 |
100 | 01/28/2009 11/30/2010 |
4 -12 |
Begin Closeout Phase
End Closeout Phase |
12/30/2009 01/30/2010 |
|
12/30/2009 01/30/2010 |
100 | 04/01/2010 11/30/2010 |
-3 -10 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 4214 | |
Peak Period Time Savings (minutes) | 25% |
Bond Funding Cost | |
---|---|
Adopted: |
$1,165,017 |
Current Approved: |
$912,414 |
Actual Expenditures: |
$912,414 |
Status as of December 31, 2023.