TLSP (Sacramento)

Description: TLSP (Sacramento)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City Sacramento
Zip Code 95816, 95817, 95819, 95820, 95822
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0%  
Peak Delay Time Saving(minutes)  20327      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Sacramento Sompol Chatusripitak 916 808 5961   schatusripitak@cityofsacramento.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$2,862 $0 $2,862
Non-bond Funding
State/Federal*
$1,000 $0 $1,000
Local**
$210 $0 $210
Private***
$0 $0 $0
 
Total**** $4,072 $0 $4,072

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $0 $5 $5 $5 $0
Design(PS&E)
$210 $0 $210 $445 $445 $-235
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,857 $0 $3,857 $3,746 $3,746 $111
 
Total* $4,072 $0 $4,072 $4,196 $4,196 $-124

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/15/2008 

07/30/2008 
 

 
04/15/2008 

07/30/2008 
100  04/15/2008 

07/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2008 

02/28/2009 
 

 
08/01/2008 

02/28/2009 
100  08/01/2008 

07/30/2010 


-17 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  07/30/2008 

12/31/2009 


Begin Construction Phase

End Construction Phase
06/30/2009 

06/30/2010 
04/08/2010 

05/05/2011 
06/30/2010 

05/31/2011 
100  03/01/2010 

05/31/2011 


Begin Closeout Phase

End Closeout Phase
07/15/2010 

12/31/2010 
05/11/2011 

 
06/15/2011 

12/31/2011 
100  06/15/2011 

12/31/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0%
Peak Delay Time Saving(minutes) 20327

Bond Funding Cost
Adopted:
$2,862,000
Current Approved:
$2,862,000
Actual Expenditures:
$2,862,000

 

Status as of December 31, 2023.