Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Florin Road |
Description: Florin Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento County |
City | |
Zip Code | 95823, 95828 |
Senate District |
06 |
Assembly District | 09 |
Congressional District | 05 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 18586 | |
Peak Period Time Savings (minutes) | 15% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Sacramento County | Doug Maas | 916 875 5545 | maasd@saccounty.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$401 | $0 | $401 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$151 | $0 | $151 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $552 | $0 | $552 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1 | $0 | $1 | $1 | $1 | $0 | |
Design(PS&E) |
$50 | $0 | $50 | $26 | $26 | $24 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$501 | $0 | $501 | $546 | $546 | $-45 | |
Total* | $552 | $0 | $552 | $573 | $573 | $-21 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/30/2008 09/30/2008 |
|
08/30/2008 09/30/2008 |
100 | 11/25/2008 12/02/2008 |
-2 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2008 12/30/2008 |
10/14/2009 |
09/30/2008 05/31/2009 |
100 | 12/30/2008 05/31/2009 |
-3 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2009 04/30/2009 |
10/14/2009 10/14/2009 |
06/30/2009 04/30/2010 |
100 | 06/22/2009 07/27/2010 |
0 -3 |
Begin Closeout Phase
End Closeout Phase |
05/30/2009 09/30/2009 |
10/14/2009 |
05/30/2010 09/30/2010 |
100 | 07/28/2010 02/10/2011 |
-2 -4 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 18586 | |
Peak Period Time Savings (minutes) | 15% |
Bond Funding Cost | |
---|---|
Adopted: |
$401,000 |
Current Approved: |
$401,000 |
Actual Expenditures: |
$401,000 |
Status as of December 31, 2023.