Florin Road

Description: Florin Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City
Zip Code 95823, 95828
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  18586      
Peak Period Time Savings (minutes)      15%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Sacramento County Doug Maas 916 875 5545   maasd@saccounty.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$401 $0 $401
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$151 $0 $151
Private***
$0 $0 $0
 
Total**** $552 $0 $552

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $0 $1 $1 $1 $0
Design(PS&E)
$50 $0 $50 $26 $26 $24
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$501 $0 $501 $546 $546 $-45
 
Total* $552 $0 $552 $573 $573 $-21

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2008 

09/30/2008 
 

 
08/30/2008 

09/30/2008 
100  11/25/2008 

12/02/2008 
-2 

-2 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2008 

12/30/2008 
 

10/14/2009 
09/30/2008 

05/31/2009 
100  12/30/2008 

05/31/2009 
-3 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2009 

04/30/2009 
10/14/2009 

10/14/2009 
06/30/2009 

04/30/2010 
100  06/22/2009 

07/27/2010 


-3 
Begin Closeout Phase

End Closeout Phase
05/30/2009 

09/30/2009 
10/14/2009 

 
05/30/2010 

09/30/2010 
100  07/28/2010 

02/10/2011 
-2 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 18586
Peak Period Time Savings (minutes) 15%

Bond Funding Cost
Adopted:
$401,000
Current Approved:
$401,000
Actual Expenditures:
$401,000

 

Status as of December 31, 2023.