Caltrans Logo

Madison Ave.

Description: Madison Ave.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City
Zip Code 95608, 95610, 95628, 95660, 95841, 95842
 
Senate District
01
Assembly District 05
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  13010      
Peak Period Time Savings (minutes)      2%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Sacramento County Doug Maas 916 875 5545   maasd@saccounty.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$142 $0 $142
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$510 $0 $510
Private***
$0 $0 $0
 
Total**** $652 $0 $652

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $0 $1 $1 $1 $0
Design(PS&E)
$24 $0 $24 $24 $24 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$627 $0 $627 $669 $669 $-42
 
Total* $652 $0 $652 $693 $693 $-41

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/30/2008 

07/30/2008 
 

 
06/30/2008 

07/30/2008 
100  08/04/2008 

08/14/2008 
-1 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2007 

08/30/2008 
 

 
10/30/2007 

08/30/2008 
100  10/30/2007 

08/30/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2008 

12/30/2008 
 

07/09/2009 
09/30/2008 

02/01/2009 
100  09/23/2008 

02/28/2009 


-1 
Begin Closeout Phase

End Closeout Phase
01/30/2009 

04/30/2009 
07/09/2009 

 
02/01/2009 

04/30/2009 
100  02/28/2009 

07/31/2009 
-1 

-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 13010
Peak Period Time Savings (minutes) 2%

Bond Funding Cost
Adopted:
$142,000
Current Approved:
$142,000
Actual Expenditures:
$142,000

 

Status as of December 31, 2023.