Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Madison Ave. |
Description: Madison Ave.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento County |
City | |
Zip Code | 95608, 95610, 95628, 95660, 95841, 95842 |
Senate District |
01 |
Assembly District | 05 |
Congressional District | 05 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 13010 | |
Peak Period Time Savings (minutes) | 2% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Sacramento County | Doug Maas | 916 875 5545 | maasd@saccounty.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$142 | $0 | $142 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$510 | $0 | $510 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $652 | $0 | $652 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1 | $0 | $1 | $1 | $1 | $0 | |
Design(PS&E) |
$24 | $0 | $24 | $24 | $24 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$627 | $0 | $627 | $669 | $669 | $-42 | |
Total* | $652 | $0 | $652 | $693 | $693 | $-41 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/30/2008 07/30/2008 |
|
06/30/2008 07/30/2008 |
100 | 08/04/2008 08/14/2008 |
-1 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2007 08/30/2008 |
|
10/30/2007 08/30/2008 |
100 | 10/30/2007 08/30/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2008 12/30/2008 |
07/09/2009 |
09/30/2008 02/01/2009 |
100 | 09/23/2008 02/28/2009 |
0 -1 |
Begin Closeout Phase
End Closeout Phase |
01/30/2009 04/30/2009 |
07/09/2009 |
02/01/2009 04/30/2009 |
100 | 02/28/2009 07/31/2009 |
-1 -3 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 13010 | |
Peak Period Time Savings (minutes) | 2% |
Bond Funding Cost | |
---|---|
Adopted: |
$142,000 |
Current Approved: |
$142,000 |
Actual Expenditures: |
$142,000 |
Status as of December 31, 2023.