Bonita Road, Sweetwater Road, Briarwood Road |
Description: Bonita Road, Sweetwater Road, Briarwood Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | |
Zip Code | 91902 |
Senate District |
36, 40 |
Assembly District | 78, 79 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 20% | |
Peak Delay Time Saving(minutes) | 6422 | |
Peak Period Time Savings (minutes) | 23% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
San Diego County | Steve Ron | 858-694-2567 | steve.ron@sdcounty.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$718 | $-86 | $632 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$780 | $-93 | $687 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,498 | $-178 | $1,320 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$25 | $-20 | $5 | $175 | $175 | $-170 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,473 | $-158 | $1,315 | $1,383 | $1,383 | $-69 | |
Total* | $1,498 | $-178 | $1,320 | $1,559 | $1,559 | $-239 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/15/2008 09/01/2008 |
|
05/15/2008 09/01/2008 |
100 | 02/15/2009 04/15/2009 |
-9 -8 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/31/2008 04/01/2009 |
06/26/2008 08/11/2010 |
09/08/2009 10/31/2010 |
100 | 09/08/2009 12/20/2010 |
0 -2 |
Begin Closeout Phase
End Closeout Phase |
04/15/2009 04/30/2009 |
08/11/2010 |
01/01/2011 01/04/2011 |
100 | 12/21/2010 08/31/2011 |
0 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 20% | |
Peak Delay Time Saving(minutes) | 6422 | |
Peak Period Time Savings (minutes) | 23% |
Bond Funding Cost | |
---|---|
Adopted: |
$718,000 |
Current Approved: |
$632,494 |
Actual Expenditures: |
$632,494 |
Status as of December 31, 2023.