Caltrans Logo

Bonita Road, Sweetwater Road, Briarwood Road

Description: Bonita Road, Sweetwater Road, Briarwood Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City
Zip Code 91902
 
Senate District
36, 40
Assembly District 78, 79
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      20%  
Peak Delay Time Saving(minutes)  6422      
Peak Period Time Savings (minutes)      23%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Diego County Steve Ron 858-694-2567   steve.ron@sdcounty.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$718 $-86 $632
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$780 $-93 $687
Private***
$0 $0 $0
 
Total**** $1,498 $-178 $1,320

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $-20 $5 $175 $175 $-170
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,473 $-158 $1,315 $1,383 $1,383 $-69
 
Total* $1,498 $-178 $1,320 $1,559 $1,559 $-239

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/15/2008 

09/01/2008 
 

 
05/15/2008 

09/01/2008 
100  02/15/2009 

04/15/2009 
-9 

-8 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/31/2008 

04/01/2009 
06/26/2008 

08/11/2010 
09/08/2009 

10/31/2010 
100  09/08/2009 

12/20/2010 


-2 
Begin Closeout Phase

End Closeout Phase
04/15/2009 

04/30/2009 
08/11/2010 

 
01/01/2011 

01/04/2011 
100  12/21/2010 

08/31/2011 


-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 20%
Peak Delay Time Saving(minutes) 6422
Peak Period Time Savings (minutes) 23%

Bond Funding Cost
Adopted:
$718,000
Current Approved:
$632,494
Actual Expenditures:
$632,494

 

Status as of December 31, 2023.