Franklin, Gough & Polk Streets

Description: Franklin, Gough & Polk Streets

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco County
City San Francisco
Zip Code 94102
 
Senate District
08
Assembly District 12
Congressional District 08, 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  25901      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Francisco MunicipalTransportation Agency Ramon Zamora 415 701 5668   Ramon.Zamora@sfmta.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$5,110 $0 $5,110
Non-bond Funding
State/Federal*
$5,110 $0 $5,110
Local**
$1,800 $0 $1,800
Private***
$0 $0 $0
 
Total**** $12,020 $0 $12,020

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,800 $0 $1,800 $1,800 $1,800 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$10,220 $0 $10,220 $10,220 $10,220 $0
 
Total* $12,020 $0 $12,020 $12,020 $12,020 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2009 

12/31/2009 
 

 
07/01/2009 

12/31/2009 
100  07/01/2009 

12/31/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

12/31/2008 
08/21/2008 

08/21/2008 
07/01/2009 

12/31/2009 
100  07/01/2009 

12/31/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2009 

12/31/2010 
08/21/2008 

08/21/2008 
01/01/2010 

12/31/2013 
100  01/01/2010 

08/30/2014 


-8 
Begin Closeout Phase

End Closeout Phase
01/01/2011 

06/30/2011 
08/21/2008 

 
01/01/2014 

06/30/2014 
100  01/01/2016 

06/30/2016 
-24 

-24 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 25901

Bond Funding Cost
Adopted:
$5,110,000
Current Approved:
$5,110,000
Actual Expenditures:
$5,110,000

 

Status as of December 31, 2023.