ATMS Expansion |
Description: ATMS Expansion
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | San Leandro |
Zip Code | 94577 |
Senate District |
10 |
Assembly District | 18 |
Congressional District | 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 5% | |
Peak Delay Time Saving(minutes) | 11177 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
San Leandro | Reh-Lin-Chen | 510 577 3438 | rchen@ci.san-leandro.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$350 | $0 | $350 | ||||
Non-bond Funding | |||||||
State/Federal* |
$184 | $0 | $184 | ||||
Local** |
$24 | $0 | $24 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $558 | $0 | $558 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$558 | $0 | $558 | $558 | $558 | $0 | |
Total* | $558 | $0 | $558 | $558 | $558 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/30/2008 11/30/2008 |
|
07/30/2008 11/30/2008 |
100 | 07/30/2008 11/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2008 01/30/2009 |
03/25/2008 |
11/30/2008 06/30/2009 |
100 | 11/30/2008 06/30/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/30/2009 01/30/2009 |
|
01/30/2009 01/30/2009 |
100 | 01/30/2009 01/30/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2009 05/30/2009 |
03/25/2008 01/19/2011 |
07/16/2009 06/30/2011 |
100 | 07/16/2009 06/30/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2009 06/30/2009 |
01/19/2011 |
07/30/2011 09/30/2011 |
100 | 07/01/2011 03/31/2012 |
1 -6 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 5% | |
Peak Delay Time Saving(minutes) | 11177 |
Bond Funding Cost | |
---|---|
Adopted: |
$350,000 |
Current Approved: |
$350,000 |
Actual Expenditures: |
$350,000 |
Status as of December 31, 2023.