Proposition 1B
Bond Accountability
Rancho Santa Fe Road |
Description: Rancho Santa Fe Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | San Marcos |
Zip Code | 92069 |
Senate District |
38 |
Assembly District | 74 |
Congressional District | 50 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 5250 | |
Peak Period Time Savings (minutes) | 25% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
San Marcos | Mike Rafael | 760 744 1050 | mrafael@san-marcos.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$266 | $-2 | $264 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$95 | $-0 | $95 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $361 | $-2 | $359 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$25 | $-0 | $25 | $32 | $32 | $-7 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$336 | $-2 | $334 | $350 | $350 | $-16 | |
Total* | $361 | $-2 | $359 | $382 | $382 | $-23 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/01/2008 01/01/2009 |
|
11/01/2008 01/01/2009 |
100 | 08/01/2008 09/01/2009 |
3 -8 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2008 02/01/2009 |
|
11/01/2008 11/01/2009 |
100 | 11/01/2008 01/19/2010 |
0 -3 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2009 06/01/2009 |
08/11/2010 08/11/2010 |
04/13/2010 08/02/2010 |
100 | 04/13/2010 10/30/2010 |
0 -3 |
Begin Closeout Phase
End Closeout Phase |
06/01/2009 06/30/2009 |
08/11/2010 |
09/01/2010 10/01/2010 |
100 | 11/01/2010 03/31/2011 |
-2 -6 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 5250 | |
Peak Period Time Savings (minutes) | 25% |
Bond Funding Cost | |
---|---|
Adopted: |
$266,000 |
Current Approved: |
$264,024 |
Actual Expenditures: |
$263,298 |
Status as of December 31, 2023.