Rancho Santa Fe Road

Description: Rancho Santa Fe Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City San Marcos
Zip Code 92069
 
Senate District
38
Assembly District 74
Congressional District 50
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0%  
Peak Delay Time Saving(minutes)  5250      
Peak Period Time Savings (minutes)      25%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Marcos Mike Rafael 760 744 1050   mrafael@san-marcos.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$266 $-2 $264
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$95 $-0 $95
Private***
$0 $0 $0
 
Total**** $361 $-2 $359

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $-0 $25 $32 $32 $-7
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$336 $-2 $334 $350 $350 $-16
 
Total* $361 $-2 $359 $382 $382 $-23

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2008 

01/01/2009 
 

 
11/01/2008 

01/01/2009 
100  08/01/2008 

09/01/2009 


-8 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2008 

02/01/2009 
 

 
11/01/2008 

11/01/2009 
100  11/01/2008 

01/19/2010 


-3 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2009 

06/01/2009 
08/11/2010 

08/11/2010 
04/13/2010 

08/02/2010 
100  04/13/2010 

10/30/2010 


-3 
Begin Closeout Phase

End Closeout Phase
06/01/2009 

06/30/2009 
08/11/2010 

 
09/01/2010 

10/01/2010 
100  11/01/2010 

03/31/2011 
-2 

-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0%
Peak Delay Time Saving(minutes) 5250
Peak Period Time Savings (minutes) 25%

Bond Funding Cost
Adopted:
$266,000
Current Approved:
$264,024
Actual Expenditures:
$263,298

 

Status as of December 31, 2023.