San Marcos Blvd. Smart Corridor

Description: San Marcos Blvd. Smart Corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City San Marcos
Zip Code 92069
 
Senate District
38
Assembly District 74
Congressional District 50
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      25%  
Peak Delay Time Saving(minutes)  17893      
Peak Period Time Savings (minutes)  7,600    7,600  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Marcos Omar Dayani 760 744 1050   odayani@san-marcos.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$549 $-9 $540
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$137 $0 $137
Private***
$0 $0 $0
 
Total**** $686 $-9 $677

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$40 $0 $40 $0 $0 $40
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$646 $-9 $637 $667 $667 $-30
 
Total* $686 $-9 $677 $668 $668 $9

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

11/26/2008 
 

 
06/01/2008 

11/26/2008 
100  06/01/2008 

10/31/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/23/2008 

03/15/2009 
 

05/05/2011 
12/23/2008 

06/30/2011 
100  11/06/2008 

07/15/2011 


Begin Closeout Phase

End Closeout Phase
04/15/2009 

06/15/2009 
05/11/2011 

 
07/15/2011 

09/30/2011 
100  07/15/2011 

11/02/2011 


-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 25%
Peak Delay Time Saving(minutes) 17893
Peak Period Time Savings (minutes) 7,600 7,600

Bond Funding Cost
Adopted:
$549,000
Current Approved:
$540,000
Actual Expenditures:
$539,597

 

Status as of December 31, 2023.