Smart Corridor Projects

Description: Smart Corridor Projects

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo County
City Belmont, Burlingame, Foster City, Millbrae, San Bruno, San Carlos, San Mateo
Zip Code 94063, 94401, 94402, 94403, 94404, 94497
 
Senate District
11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  53318      
Peak Period Time Savings (minutes)      53318  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
City/County Association of Governments of San Mateo County John Hoang 650 363 4105   jhoang@smcgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$10,000 $6,238 $16,238
Non-bond Funding
State/Federal*
$5,962 $6,605 $12,567
Local**
$4,403 $879 $5,282
Private***
$0 $0 $0
 
Total**** $20,365 $13,722 $34,087

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$321 $79 $400 $350 $350 $50
Design(PS&E)
$2,359 $2,180 $4,539 $4,359 $4,359 $180
Right of Way
$80 $-50 $30 $30 $30 $0
Construction
$17,605 $11,513 $29,118 $29,512 $29,512 $-394
 
Total* $20,365 $13,722 $34,087 $34,251 $34,251 $-164

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2008 

11/01/2008 
 

06/11/2009 
04/01/2008 

09/30/2009 
100  04/01/2008 

01/19/2010 


-4 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2008 

12/01/2009 
12/01/2009 

12/01/2009 
10/01/2008 

12/01/2009 
100  08/01/2009 

11/30/2010 
-10 

-12 
Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

12/01/2009 
 

06/11/2010 
01/01/2009 

10/30/2010 
100  01/01/2009 

03/01/2011 


-4 
Begin Construction Phase

End Construction Phase
12/01/2009 

11/01/2011 
 

 
12/01/2009 

06/01/2013 
100  10/04/2010 

03/01/2018 
-10 

-58 
Begin Closeout Phase

End Closeout Phase
12/01/2011 

04/01/2012 
03/28/2012 

 
06/01/2013 

12/01/2013 
100  03/02/2018 

09/01/2018 
-58 

-58 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 53318
Peak Period Time Savings (minutes) 53318

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$16,237,890
Actual Expenditures:
$16,236,890

 

Status as of December 31, 2023.