Caltrans Logo

Bollinger Canyon

Description: Bollinger Canyon

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa County
City San Ramon
Zip Code 94583
 
Senate District
07
Assembly District 11
Congressional District 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      35%  
Peak Delay Time Saving(minutes)  4620      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Ramon Mike Talley 925 973 2654   mtalley@sanramon.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$475 $0 $475
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$264 $-0 $264
Private***
$0 $0 $0
 
Total**** $739 $-0 $739

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$10 $0 $10 $3 $3 $7
Design(PS&E)
$20 $0 $20 $15 $15 $5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$709 $-0 $709 $891 $891 $-182
 
Total* $739 $-0 $739 $909 $909 $-170

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/31/2008 

12/30/2008 
06/01/2009 

06/01/2009 
03/03/2009 

04/30/2009 
100  03/03/2009 

04/30/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/28/2009 

03/14/2009 
06/01/2009 

06/01/2009 
05/28/2009 

07/14/2009 
100  05/28/2009 

07/14/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/26/2009 

11/10/2009 
06/01/2009 

01/28/2016 
09/26/2009 

03/10/2010 
100  09/26/2009 

03/10/2010 


Begin Closeout Phase

End Closeout Phase
11/30/2009 

01/31/2010 
06/01/2009 

 
03/30/2010 

05/31/2010 
100  12/15/2010 

06/16/2017 
-9 

-86 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 35%
Peak Delay Time Saving(minutes) 4620

Bond Funding Cost
Adopted:
$475,000
Current Approved:
$475,000
Actual Expenditures:
$474,398

 

Status as of December 31, 2023.