Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
TLSP Tier 3 & 4 |
Description: TLSP Tier 3 & 4
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino County |
City | |
Zip Code | 91701, 91708, 91709, 91710, 91729, 91730, 91737, 91739, 91758, 91761, 91762, 91763, 91764, 91784, 91785, 91786, 92313, 92324, 92331, 92334, 92335, 92336, 92337, 92346, 92350, 92354, 92357, 92373, 92374, 92375, 92376, 92377, 92401, 92402, 92403, 92404, 92405, 92406, 92407, 92408, 92410, 92411, 92412, 92413, 92414, 92415, 92418, 92423, 92424, 92427 |
Senate District |
29, 31, 32 |
Assembly District | 59, 60, 61, 62, 63 |
Congressional District | 26, 41, 42, 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 15% | |
Peak Delay Time Saving(minutes) | 121742 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
San Bernardino Associated Governments | Philip Chu | 909 8848276 | pchu@sanbag.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$2,000 | $-463 | $1,537 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,500 | $219 | $4,719 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,500 | $-244 | $6,256 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,500 | $-1,360 | $140 | $20 | $20 | $120 | |
Design(PS&E) |
$1,000 | $1,287 | $2,287 | $2,670 | $2,670 | $-382 | |
Right of Way |
$0 | $5 | $5 | $0 | $0 | $5 | |
Construction |
$4,000 | $-176 | $3,824 | $3,304 | $3,304 | $520 | |
Total* | $6,500 | $-244 | $6,256 | $5,994 | $5,994 | $262 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/30/2008 06/30/2009 |
05/01/2009 |
10/30/2008 09/30/2009 |
100 | 03/02/2009 04/09/2010 |
-4 -6 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/2009 04/30/2010 |
05/01/2009 |
10/31/2009 04/30/2010 |
100 | 03/02/2009 12/31/2011 |
8 -20 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2010 10/30/2011 |
08/11/2010 08/11/2010 |
12/31/2010 06/29/2012 |
100 | 12/31/2010 01/31/2012 |
0 5 |
Begin Closeout Phase
End Closeout Phase |
11/30/2011 12/30/2011 |
08/11/2010 |
07/01/2012 12/31/2012 |
100 | 11/10/2011 03/03/2014 |
8 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 15% | |
Peak Delay Time Saving(minutes) | 121742 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,000,000 |
Current Approved: |
$1,537,041 |
Actual Expenditures: |
$1,537,041 |
Status as of December 31, 2023.