Caltrans Logo

TLSP Tier 3 & 4

Description: TLSP Tier 3 & 4

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino County
City
Zip Code 91701, 91708, 91709, 91710, 91729, 91730, 91737, 91739, 91758, 91761, 91762, 91763, 91764, 91784, 91785, 91786, 92313, 92324, 92331, 92334, 92335, 92336, 92337, 92346, 92350, 92354, 92357, 92373, 92374, 92375, 92376, 92377, 92401, 92402, 92403, 92404, 92405, 92406, 92407, 92408, 92410, 92411, 92412, 92413, 92414, 92415, 92418, 92423, 92424, 92427
 
Senate District
29, 31, 32
Assembly District 59, 60, 61, 62, 63
Congressional District 26, 41, 42, 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      15%  
Peak Delay Time Saving(minutes)  121742      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Bernardino Associated Governments Philip Chu 909 8848276   pchu@sanbag.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$2,000 $-463 $1,537
Non-bond Funding
State/Federal*
$4,500 $219 $4,719
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $6,500 $-244 $6,256

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,500 $-1,360 $140 $20 $20 $120
Design(PS&E)
$1,000 $1,287 $2,287 $2,670 $2,670 $-382
Right of Way
$0 $5 $5 $0 $0 $5
Construction
$4,000 $-176 $3,824 $3,304 $3,304 $520
 
Total* $6,500 $-244 $6,256 $5,994 $5,994 $262

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/30/2008 

06/30/2009 
 

05/01/2009 
10/30/2008 

09/30/2009 
100  03/02/2009 

04/09/2010 
-4 

-6 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2009 

04/30/2010 
05/01/2009 

 
10/31/2009 

04/30/2010 
100  03/02/2009 

12/31/2011 


-20 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2010 

10/30/2011 
08/11/2010 

08/11/2010 
12/31/2010 

06/29/2012 
100  12/31/2010 

01/31/2012 


Begin Closeout Phase

End Closeout Phase
11/30/2011 

12/30/2011 
08/11/2010 

 
07/01/2012 

12/31/2012 
100  11/10/2011 

03/03/2014 


-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 15%
Peak Delay Time Saving(minutes) 121742

Bond Funding Cost
Adopted:
$2,000,000
Current Approved:
$1,537,041
Actual Expenditures:
$1,537,041

 

Status as of December 31, 2023.