Caltrans Logo

At-grade Crossing Traffic Synchronization

Description: At-grade Crossing Traffic Synchronization

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City San Diego
Zip Code 92101
 
Senate District
39
Assembly District 76, 79
Congressional District 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      66%  
Peak Delay Time Saving(minutes)  11086      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Diego Association of Governments Alex Estrella 619 699 1928   aes@sandag.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$820 $0 $820
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$200 $80 $280
Private***
$0 $0 $0
 
Total**** $1,020 $80 $1,100

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $80 $80 $0 $0 $80
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,020 $0 $1,020 $1,309 $1,309 $-289
 
Total* $1,020 $80 $1,100 $1,309 $1,309 $-209

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2004 

06/30/2008 
 

 
07/01/2004 

06/30/2008 
100  07/01/2004 

06/30/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

09/30/2010 
 

06/27/2012 
10/01/2008 

12/31/2012 
100  12/01/2008 

10/31/2014 
-2 

-22 
Begin Closeout Phase

End Closeout Phase
10/01/2010 

03/31/2011 
06/27/2012 

 
01/01/2013 

03/30/2013 
100  11/03/2014 

06/30/2015 
-22 

-27 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 66%
Peak Delay Time Saving(minutes) 11086

Bond Funding Cost
Adopted:
$820,000
Current Approved:
$820,000
Actual Expenditures:
$820,000

 

Status as of December 31, 2023.