Caltrans Logo

I-15 Corridor

Description: I-15 Corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Escondido, Poway, San Diego
Zip Code 92025, 92026, 92064, 92128, 92131
 
Senate District
36, 38, 39
Assembly District 74, 75, 77
Congressional District 49, 50, 52
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0  
Peak Delay Time Saving(minutes)  24817      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Diego Association of Governments Alex Estrella 619 699 1928   aes@sandag.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$2,162 $-8 $2,154
Non-bond Funding
State/Federal*
$150 $0 $150
Local**
$100 $0 $100
Private***
$0 $0 $0
 
Total**** $2,412 $-8 $2,404

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,412 $-8 $2,404 $2,403 $2,403 $1
 
Total* $2,412 $-8 $2,404 $2,403 $2,403 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2003 

11/30/2003 
 

 
11/30/2002 

11/30/2003 
100  11/30/2003 

11/30/2003 
-12 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

02/28/2010 
 

06/22/2011 
06/01/2010 

06/30/2011 
100  12/01/2008 

07/15/2011 
18 

Begin Closeout Phase

End Closeout Phase
03/01/2010 

05/30/2010 
06/22/2011 

 
06/01/2011 

07/30/2011 
100  07/16/2011 

07/30/2011 
-1 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0
Peak Delay Time Saving(minutes) 24817

Bond Funding Cost
Adopted:
$2,162,000
Current Approved:
$2,154,000
Actual Expenditures:
$2,153,685

 

Status as of December 31, 2023.