I-805 Corridor

Description: I-805 Corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Chula Vista, National City
Zip Code 91910, 91911, 91950
 
Senate District
39
Assembly District 79
Congressional District 40
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      14%  
Peak Delay Time Saving(minutes)  6689      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Diego Association of Governments Alex Estrella 619 699 1928   aes@sandag.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$640 $-366 $274
Non-bond Funding
State/Federal*
$150 $-86 $64
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $790 $-452 $338

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$790 $-452 $338 $364 $364 $-26
 
Total* $790 $-452 $338 $364 $364 $-26

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2002 

11/30/2003 
 

 
11/30/2002 

11/30/2003 
100  11/30/2003 

11/30/2003 
-12 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

08/31/2009 
 

 
10/01/2008 

08/31/2009 
100  12/01/2008 

08/31/2009 
-2 

Begin Closeout Phase

End Closeout Phase
09/01/2009 

12/31/2009 
 

 
09/01/2009 

12/31/2009 
100  09/01/2009 

03/02/2015 


-63 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 14%
Peak Delay Time Saving(minutes) 6689

Bond Funding Cost
Adopted:
$640,000
Current Approved:
$273,739
Actual Expenditures:
$273,739

 

Status as of December 31, 2023.