Transit Signal Priority

Description: Transit Signal Priority

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Escondido, San Diego
Zip Code 92029, 92122
 
Senate District
36, 38, 39, 40
Assembly District 66, 73, 74, 75, 76, 77, 78, 79
Congressional District 49, 50, 51, 52, 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0  
Peak Delay Time Saving(minutes)  12137      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
San Diego Association of Governments Alex Estrella 619 699 1928   aes@sandag.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$951 $-9 $942
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$1,996 $0 $1,996
Private***
$0 $0 $0
 
Total**** $2,947 $-9 $2,938

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,947 $-9 $2,938 $2,919 $2,919 $19
 
Total* $2,947 $-9 $2,938 $2,919 $2,919 $19

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2007 

08/30/2007 
 

 
08/30/2007 

08/30/2007 
100  08/30/2007 

08/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2007 

06/30/2008 
 

 
09/30/2007 

06/30/2008 
100  09/30/2007 

09/30/2007 


Begin Right of Way Phase

End Right of Way Phase
06/30/2008 

06/30/2008 
 

 
06/30/2008 

06/30/2008 
100  06/30/2008 

06/30/2008 


Begin Construction Phase

End Construction Phase
11/30/2008 

12/30/2009 
 

06/27/2012 
11/30/2008 

11/30/2012 
100  11/30/2008 

12/30/2012 


-1 
Begin Closeout Phase

End Closeout Phase
01/30/2010 

05/30/2010 
06/27/2012 

 
12/01/2012 

02/28/2013 
100  01/01/2013 

07/31/2014 
-1 

-17 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0
Peak Delay Time Saving(minutes) 12137

Bond Funding Cost
Adopted:
$951,000
Current Approved:
$942,000
Actual Expenditures:
$941,775

 

Status as of December 31, 2023.