Caltrans Logo

County Expressway TDCS for TLSP

Description: County Expressway TDCS for TLSP

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara County
City
Zip Code 94022, 94024, 94040, 94041, 94043, 94085, 94086, 94087, 94089, 94301, 94304, 94305, 94306, 95008, 95014, 95035, 95050, 95051, 95054, 95070, 95111, 95116, 95117, 95118, 95120, 95121, 95122, 95123, 95125, 95127, 95129, 95130, 95131, 95134, 95136, 95148
 
Senate District
10, 11, 13, 15
Assembly District 20, 21, 22, 23, 24, 27, 28
Congressional District 13, 14, 15, 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0%  
Peak Delay Time Saving(minutes)  103382      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Santa Clara County Masoud Akbarzadeh 408 494 1336   masoud.akbarzadeh@rda.sccgov.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$900 $0 $900
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$130 $0 $130
Private***
$0 $0 $0
 
Total**** $1,030 $0 $1,030

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$40 $0 $40 $45 $45 $-5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$990 $0 $990 $1,020 $1,020 $-30
 
Total* $1,030 $0 $1,030 $1,065 $1,065 $-35

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

07/01/2009 
 

10/13/2009 
07/01/2008 

03/30/2010 
100  07/01/2008 

07/01/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2009 

09/30/2010 
10/13/2009 

10/13/2009 
10/01/2010 

11/30/2011 
100  10/01/2010 

11/30/2011 


Begin Closeout Phase

End Closeout Phase
12/30/2010 

04/30/2011 
10/01/2009 

 
12/31/2011 

04/30/2012 
100  12/31/2011 

04/30/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0%
Peak Delay Time Saving(minutes) 103382

Bond Funding Cost
Adopted:
$900,000
Current Approved:
$900,000
Actual Expenditures:
$900,000

 

Status as of December 31, 2023.