Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
County Expressway TDCS for TLSP |
Description: County Expressway TDCS for TLSP
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara County |
City | |
Zip Code | 94022, 94024, 94040, 94041, 94043, 94085, 94086, 94087, 94089, 94301, 94304, 94305, 94306, 95008, 95014, 95035, 95050, 95051, 95054, 95070, 95111, 95116, 95117, 95118, 95120, 95121, 95122, 95123, 95125, 95127, 95129, 95130, 95131, 95134, 95136, 95148 |
Senate District |
10, 11, 13, 15 |
Assembly District | 20, 21, 22, 23, 24, 27, 28 |
Congressional District | 13, 14, 15, 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 103382 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Santa Clara County | Masoud Akbarzadeh | 408 494 1336 | masoud.akbarzadeh@rda.sccgov.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$900 | $0 | $900 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$130 | $0 | $130 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,030 | $0 | $1,030 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$40 | $0 | $40 | $45 | $45 | $-5 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$990 | $0 | $990 | $1,020 | $1,020 | $-30 | |
Total* | $1,030 | $0 | $1,030 | $1,065 | $1,065 | $-35 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 07/01/2009 |
10/13/2009 |
07/01/2008 03/30/2010 |
100 | 07/01/2008 07/01/2009 |
0 9 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2009 09/30/2010 |
10/13/2009 10/13/2009 |
10/01/2010 11/30/2011 |
100 | 10/01/2010 11/30/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/30/2010 04/30/2011 |
10/01/2009 |
12/31/2011 04/30/2012 |
100 | 12/31/2011 04/30/2012 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 103382 |
Bond Funding Cost | |
---|---|
Adopted: |
$900,000 |
Current Approved: |
$900,000 |
Actual Expenditures: |
$900,000 |
Status as of December 31, 2023.