Steele Lane / Guerneville

Description: Steele Lane / Guerneville

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma County
City Santa Rosa
Zip Code 95401
 
Senate District
02
Assembly District 07
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      25%  
Peak Delay Time Saving(minutes)  11779      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Santa Rosa Rob Sprinkle 707-543-3817   rsprinkle@srcity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$1,100 $0 $1,100
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$500 $0 $500
Private***
$0 $0 $0
 
Total**** $1,600 $0 $1,600

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$42 $0 $42 $0 $0 $42
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,558 $0 $1,558 $1,569 $1,569 $-12
 
Total* $1,600 $0 $1,600 $1,569 $1,569 $31

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/07/2008 

02/13/2008 
 

 
02/07/2008 

02/13/2008 
100  02/07/2008 

02/13/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

08/01/2008 
 

 
06/01/2008 

08/01/2008 
100  06/01/2008 

08/01/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2008 

12/30/2008 
 

07/09/2009 
08/01/2008 

09/01/2009 
100  12/09/2008 

10/30/2009 
-4 

-2 
Begin Closeout Phase

End Closeout Phase
01/01/2009 

01/28/2009 
 

 
10/30/2009 

12/28/2009 
100  10/30/2009 

12/31/2009 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 25%
Peak Delay Time Saving(minutes) 11779

Bond Funding Cost
Adopted:
$1,100,000
Current Approved:
$1,100,000
Actual Expenditures:
$1,099,647

 

Status as of December 31, 2023.