Magnolia Avenue

Description: Magnolia Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Santee
Zip Code 92071, 92072
 
Senate District
36
Assembly District 77
Congressional District 52
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0  
Peak Delay Time Saving(minutes)  1824      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Santee Minjie mei 619-258-4100   mmei@ci.santee.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$116 $-23 $93
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$49 $-5 $44
Private***
$0 $0 $0
 
Total**** $165 $-28 $137

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2 $0 $2 $2 $2 $0
Design(PS&E)
$18 $1 $19 $19 $19 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$145 $-29 $116 $116 $116 $0
 
Total* $165 $-28 $137 $137 $137 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/30/2008 

09/30/2008 
 

 
06/30/2008 

12/31/2008 
100  10/01/2008 

12/16/2008 
-3 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2008 

03/30/2009 
 

 
10/30/2009 

12/22/2009 
100  10/31/2008 

12/22/2009 
12 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/30/2009 

09/30/2009 
10/15/2009 

10/15/2009 
03/30/2010 

05/30/2010 
100  02/16/2010 

10/31/2010 


-5 
Begin Closeout Phase

End Closeout Phase
09/30/2009 

10/30/2009 
10/15/2009 

 
06/30/2010 

08/31/2010 
100  01/01/2011 

12/31/2012 
-6 

-28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0
Peak Delay Time Saving(minutes) 1824

Bond Funding Cost
Adopted:
$116,000
Current Approved:
$93,030
Actual Expenditures:
$93,030

 

Status as of December 31, 2023.