Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Magnolia Avenue |
Description: Magnolia Avenue
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | Santee |
Zip Code | 92071, 92072 |
Senate District |
36 |
Assembly District | 77 |
Congressional District | 52 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0 | |
Peak Delay Time Saving(minutes) | 1824 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Santee | Minjie mei | 619-258-4100 | mmei@ci.santee.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$116 | $-23 | $93 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$49 | $-5 | $44 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $165 | $-28 | $137 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2 | $0 | $2 | $2 | $2 | $0 | |
Design(PS&E) |
$18 | $1 | $19 | $19 | $19 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$145 | $-29 | $116 | $116 | $116 | $0 | |
Total* | $165 | $-28 | $137 | $137 | $137 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/30/2008 09/30/2008 |
|
06/30/2008 12/31/2008 |
100 | 10/01/2008 12/16/2008 |
-3 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2008 03/30/2009 |
|
10/30/2009 12/22/2009 |
100 | 10/31/2008 12/22/2009 |
12 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/30/2009 09/30/2009 |
10/15/2009 10/15/2009 |
03/30/2010 05/30/2010 |
100 | 02/16/2010 10/31/2010 |
1 -5 |
Begin Closeout Phase
End Closeout Phase |
09/30/2009 10/30/2009 |
10/15/2009 |
06/30/2010 08/31/2010 |
100 | 01/01/2011 12/31/2012 |
-6 -28 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0 | |
Peak Delay Time Saving(minutes) | 1824 |
Bond Funding Cost | |
---|---|
Adopted: |
$116,000 |
Current Approved: |
$93,030 |
Actual Expenditures: |
$93,030 |
Status as of December 31, 2023.