Caltrans Logo

Grant Line Road

Description: Grant Line Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin County
City Tracy
Zip Code 95304, 95376
 
Senate District
05
Assembly District 17
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      14%  
Peak Delay Time Saving(minutes)  5460      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Tracy Kuldeep Sharma 209-831-6400   kuldeeps@ci.tracy.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$300 $-137 $163
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$100 $-46 $54
Private***
$0 $0 $0
 
Total**** $400 $-183 $217

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $-1 $4 $1 $1 $3
Design(PS&E)
$75 $-35 $40 $73 $73 $-33
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$320 $-147 $173 $179 $179 $-6
 
Total* $400 $-183 $217 $253 $253 $-36

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/30/2008 

09/30/2008 
 

 
09/30/2008 

09/30/2008 
100  11/03/2008 

01/30/2009 
-1 

-4 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2008 

12/30/2008 
 

 
10/30/2008 

03/31/2009 
100  10/01/2008 

03/31/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/30/2009 

07/30/2009 
05/06/2010 

05/06/2010 
01/01/2010 

10/02/2010 
100  12/01/2009 

09/30/2010 


Begin Closeout Phase

End Closeout Phase
08/30/2009 

10/30/2009 
 

 
11/01/2010 

12/30/2010 
100  10/01/2010 

11/30/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 14%
Peak Delay Time Saving(minutes) 5460

Bond Funding Cost
Adopted:
$300,000
Current Approved:
$162,830
Actual Expenditures:
$162,830

 

Status as of December 31, 2023.