Grant Line Road |
Description: Grant Line Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin County |
City | Tracy |
Zip Code | 95304, 95376 |
Senate District |
05 |
Assembly District | 17 |
Congressional District | 11 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 14% | |
Peak Delay Time Saving(minutes) | 5460 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Tracy | Kuldeep Sharma | 209-831-6400 | kuldeeps@ci.tracy.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$300 | $-137 | $163 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$100 | $-46 | $54 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $400 | $-183 | $217 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$5 | $-1 | $4 | $1 | $1 | $3 | |
Design(PS&E) |
$75 | $-35 | $40 | $73 | $73 | $-33 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$320 | $-147 | $173 | $179 | $179 | $-6 | |
Total* | $400 | $-183 | $217 | $253 | $253 | $-36 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/30/2008 09/30/2008 |
|
09/30/2008 09/30/2008 |
100 | 11/03/2008 01/30/2009 |
-1 -4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2008 12/30/2008 |
|
10/30/2008 03/31/2009 |
100 | 10/01/2008 03/31/2009 |
1 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/30/2009 07/30/2009 |
05/06/2010 05/06/2010 |
01/01/2010 10/02/2010 |
100 | 12/01/2009 09/30/2010 |
1 0 |
Begin Closeout Phase
End Closeout Phase |
08/30/2009 10/30/2009 |
|
11/01/2010 12/30/2010 |
100 | 10/01/2010 11/30/2010 |
1 1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 14% | |
Peak Delay Time Saving(minutes) | 5460 |
Bond Funding Cost | |
---|---|
Adopted: |
$300,000 |
Current Approved: |
$162,830 |
Actual Expenditures: |
$162,830 |
Status as of December 31, 2023.