Tracy Blvd. |
|
Description: Tracy Blvd.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Joaquin County |
| City | Tracy |
| Zip Code | 95304, 95376 |
| Senate District |
05 |
| Assembly District | 17 |
| Congressional District | 11 |
| Caltrans District |
10 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Daily Travel Time Savings (hours) | 15% | |
| Peak Delay Time Saving(minutes) | 2730 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| TLSP |
Tracy | Kuldeep Sharma | 209-831-6400 | kuldeeps@ci.tracy.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| TLSP |
$150 | $-39 | $111 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $0 | $0 | ||||
| Local** |
$50 | $-13 | $37 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $200 | $-52 | $148 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$5 | $-3 | $2 | $1 | $1 | $1 | |
| Design(PS&E) |
$35 | $-5 | $30 | $39 | $39 | $-9 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$160 | $-44 | $116 | $125 | $125 | $-8 | |
| Total* | $200 | $-52 | $148 | $164 | $164 | $-16 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
09/30/2008 09/30/2008 |
|
09/30/2008 09/30/2008 |
100 | 11/03/2008 01/30/2009 |
-1 -4 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2008 12/30/2008 |
|
10/30/2008 03/30/2009 |
100 | 10/01/2008 03/30/2009 |
1 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
03/30/2008 07/30/2009 |
04/08/2010 04/08/2010 |
01/01/2010 10/01/2010 |
100 | 12/01/2009 09/30/2010 |
1 0 |
|
Begin Closeout Phase
End Closeout Phase |
08/30/2009 10/30/2009 |
08/11/2008 |
10/01/2010 12/30/2010 |
100 | 10/01/2010 11/30/2010 |
0 1 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Daily Travel Time Savings (hours) | 15% | |
| Peak Delay Time Saving(minutes) | 2730 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$150,000 |
| Current Approved: |
$111,211 |
| Actual Expenditures: |
$111,211 |
Status as of December 31, 2025.