Caltrans Logo

North Santa Fe Avenue

Description: North Santa Fe Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Vista
Zip Code 92084
 
Senate District
38
Assembly District 74
Congressional District 49
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  3150      
Peak Period Time Savings (minutes)      27.78%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Vista Husam Hasenin 760-726-1340 X1383   hhasenin@cityofvista.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$161 $-5 $156
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$57 $-2 $55
Private***
$0 $0 $0
 
Total**** $218 $-7 $211

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$17 $0 $17 $18 $18 $-1
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$201 $-7 $194 $194 $194 $-1
 
Total* $218 $-7 $211 $212 $212 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/14/2008 

08/12/2008 
 

 
07/14/2008 

08/12/2008 
100  07/14/2008 

08/12/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/14/2008 

01/02/2009 
 

 
10/14/2008 

01/02/2009 
100  10/14/2008 

05/30/2009 


-5 
Begin Closeout Phase

End Closeout Phase
01/02/2009 

01/30/2009 
 

 
01/02/2009 

01/30/2009 
100  05/30/2009 

03/31/2010 
-5 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 3150
Peak Period Time Savings (minutes) 27.78%

Bond Funding Cost
Adopted:
$161,000
Current Approved:
$155,574
Actual Expenditures:
$155,574

 

Status as of December 31, 2023.