Ygnacio Valley Road Corridor

Description: Ygnacio Valley Road Corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa County
City Walnut Creek
Zip Code 94596, 94598
 
Senate District
07
Assembly District 15
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      10%  
Peak Delay Time Saving(minutes)  15552      
Peak Period Time Savings (minutes)      6%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Walnut Creek Simin Timuri 925-943-5899 2223   timuri@walnut-creek.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$1,489 $-28 $1,461
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$650 $-0 $650
Private***
$0 $0 $0
 
Total**** $2,139 $-28 $2,111

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$389 $0 $389 $442 $442 $-53
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,750 $-28 $1,722 $1,717 $1,717 $5
 
Total* $2,139 $-28 $2,111 $2,159 $2,159 $-48

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/30/2008 

01/30/2009 
 

 
08/30/2008 

01/30/2009 
100  09/01/2008 

04/15/2009 


-2 
Begin Right of Way Phase

End Right of Way Phase
09/30/2008 

03/30/2009 
 

 
09/30/2008 

03/30/2009 
100  09/30/2008 

03/30/2009 


Begin Construction Phase

End Construction Phase
04/30/2009 

11/30/2009 
03/24/2009 

08/11/2010 
06/30/2009 

11/01/2010 
100  06/02/2009 

03/01/2010 


Begin Closeout Phase

End Closeout Phase
11/30/2009 

01/30/2010 
10/31/2012 

 
12/01/2010 

06/01/2011 
100  03/01/2010 

11/30/2011 


-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 10%
Peak Delay Time Saving(minutes) 15552
Peak Period Time Savings (minutes) 6%

Bond Funding Cost
Adopted:
$1,489,000
Current Approved:
$1,461,000
Actual Expenditures:
$1,460,594

 

Status as of December 31, 2023.