ATCS - Echo Park / Silver Lake Phase 2 |
Description: ATCS - Echo Park / Silver Lake Phase 2
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
21, 22 |
Assembly District | 45, 46, 48 |
Congressional District | 31, 33 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 53479 | 53479 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Los Angeles | Bill Shao | (213) 972-8668 | bill.shao@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$4,504 | $-1,476 | $3,028 | ||||
Non-bond Funding | |||||||
Local** |
$1,239 | $-541 | $698 | ||||
Total**** | $5,743 | $-2,017 | $3,727 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$413 | $0 | $413 | $413 | $413 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,330 | $-2,017 | $3,313 | $3,186 | $3,186 | $127 | |
Total* | $5,743 | $-2,017 | $3,727 | $3,600 | $3,600 | $127 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/17/2008 01/17/2008 |
|
01/17/2008 01/17/2008 |
100 | 11/17/2008 11/17/2008 |
-10 -10 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2010 06/01/2011 |
08/21/2013 08/21/2013 |
12/01/2013 04/01/2014 |
100 | 09/01/2014 02/01/2015 |
-9 -10 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2011 10/01/2014 |
11/18/2015 07/17/2017 |
09/01/2015 10/31/2016 |
100 | 11/18/2015 07/31/2017 |
-3 -9 |
Begin Closeout Phase
End Closeout Phase |
10/01/2014 04/01/2015 |
03/23/2017 |
10/31/2016 04/01/2017 |
100 | 07/31/2017 03/15/2018 |
-9 -12 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 53479 | 53479 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,504,000 |
Current Approved: |
$3,028,060 |
Actual Expenditures: |
$3,028,060 |
Status as of December 31, 2023.