ATCS - Echo Park / Silver Lake Phase 2

Description: ATCS - Echo Park / Silver Lake Phase 2

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
21, 22
Assembly District 45, 46, 48
Congressional District 31, 33
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  53479    53479  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$4,504 $-1,476 $3,028
Non-bond Funding
Local**
$1,239 $-541 $698
 
Total**** $5,743 $-2,017 $3,727

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$413 $0 $413 $413 $413 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,330 $-2,017 $3,313 $3,186 $3,186 $127
 
Total* $5,743 $-2,017 $3,727 $3,600 $3,600 $127

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/17/2008 

11/17/2008 
-10 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2010 

06/01/2011 
08/21/2013 

08/21/2013 
12/01/2013 

04/01/2014 
100  09/01/2014 

02/01/2015 
-9 

-10 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

10/01/2014 
11/18/2015 

07/17/2017 
09/01/2015 

10/31/2016 
100  11/18/2015 

07/31/2017 
-3 

-9 
Begin Closeout Phase

End Closeout Phase
10/01/2014 

04/01/2015 
03/23/2017 

 
10/31/2016 

04/01/2017 
100  07/31/2017 

03/15/2018 
-9 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 53479 53479

Bond Funding Cost
Adopted:
$4,504,000
Current Approved:
$3,028,060
Actual Expenditures:
$3,028,060

 

Status as of December 31, 2023.