Automated Traffic Surveillance & Control Enhancements for an Advanced Transportation Infrastructure |
Description: ATSAC-Advanced Transportation Infrastructure
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90007, 90012, 90015, 90024, 90045, 90810, 91436 |
Senate District |
08, 24, 26, 27, 30, 35 |
Assembly District | 45, 46, 53, 54, 59, 62, 64, 66, 70 |
Congressional District | 29, 30, 33, 37, 40, 43, 44 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 31857 | 31857 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
City of Los Angeles, Department of Transportation | George Chen | 213-972-5058 | george.chen@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$18,361 | $0 | $18,361 | ||||
Non-bond Funding | |||||||
Local** |
$400 | $0 | $400 | ||||
Total**** | $18,761 | $0 | $18,761 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$400 | $0 | $400 | $0 | $0 | $400 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$18,361 | $0 | $18,361 | $12,354 | $0 | $18,361 | |
Total* | $18,761 | $0 | $18,761 | $12,354 | $0 | $18,761 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/2019 06/17/2020 |
12/03/2020 12/03/2020 |
09/01/2019 06/17/2020 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/02/2020 11/13/2020 |
12/03/2020 12/03/2020 |
01/02/2020 11/13/2020 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/13/2021 12/31/2022 |
12/03/2020 12/03/2020 |
05/31/2021 12/31/2022 |
55 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2023 03/31/2023 |
12/03/2020 |
01/01/2023 03/31/2023 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 31857 | 31857 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.