Caltrans Logo

Automated Traffic Surveillance & Control Enhancements for an Advanced Transportation Infrastructure

Description: ATSAC-Advanced Transportation Infrastructure

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90007, 90012, 90015, 90024, 90045, 90810, 91436
 
Senate District
08, 24, 26, 27, 30, 35
Assembly District 45, 46, 53, 54, 59, 62, 64, 66, 70
Congressional District 29, 30, 33, 37, 40, 43, 44
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  31857    31857  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
City of Los Angeles, Department of Transportation George Chen 213-972-5058   george.chen@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$18,361 $0 $18,361
Non-bond Funding
Local**
$400 $0 $400
 
Total**** $18,761 $0 $18,761

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$400 $0 $400 $0 $0 $400
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$18,361 $0 $18,361 $12,354 $0 $18,361
 
Total* $18,761 $0 $18,761 $12,354 $0 $18,761

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2019 

06/17/2020 
12/03/2020 

12/03/2020 
09/01/2019 

06/17/2020 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/02/2020 

11/13/2020 
12/03/2020 

12/03/2020 
01/02/2020 

11/13/2020 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/13/2021 

12/31/2022 
12/03/2020 

12/03/2020 
05/31/2021 

12/31/2022 
55   

 


Begin Closeout Phase

End Closeout Phase
01/01/2023 

03/31/2023 
12/03/2020 

 
01/01/2023 

03/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 31857 31857

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.