Smart Corridor Countywide ITS Improvements-South San Francisco Expansion

Description: Smart Corridor-South San Francisco Expansion

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Mateo
City South San Francisco
Zip Code 94080
 
Senate District
13
Assembly District 22
Congressional District 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  4425    4425  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
City of South San Francisco Angel Torres 650-829-6660   angel.torres@ssf.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$3,598 $0 $3,598
Non-bond Funding
State/Federal*
$2,284 $0 $2,284
Local**
$2,737 $0 $2,737
 
Total**** $8,619 $0 $8,619

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$100 $0 $100 $0 $0 $100
Design(PS&E)
$360 $0 $360 $360 $0 $360
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,159 $0 $8,159 $2,597 $0 $8,159
 
Total* $8,619 $0 $8,619 $2,957 $0 $8,619

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2017 

05/08/2019 
01/28/2021 

01/28/2021 
05/01/2017 

05/08/2019 
100  05/01/2017 

05/08/2019 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/29/2019 

11/01/2020 
01/28/2021 

01/28/2021 
08/29/2019 

11/01/2020 
100  08/29/2019 

11/01/2020 


Begin Right of Way Phase

End Right of Way Phase
04/17/2020 

11/01/2020 
01/28/2021 

01/28/2021 
04/17/2020 

11/01/2020 
100   

 


Begin Construction Phase

End Construction Phase
06/01/2021 

06/01/2022 
01/28/2021 

01/28/2021 
06/01/2021 

06/01/2022 
60  03/08/2022 

06/28/2024 
-9 

-25 
Begin Closeout Phase

End Closeout Phase
06/02/2022 

12/01/2022 
01/28/2021 

 
06/02/2022 

12/01/2022 
07/01/2024 

11/29/2024 
-25 

-24 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 4425 4425

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.