Civic Center Drive at Harbor Drive and I-5 At-Grade Improvements |
Description: Operational Improvements
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | |
Senate District |
40 |
Assembly District | 79 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | San Diego 5 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Mario Orso | (619) 688-2561 | mario_orso@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Mario Orso | (619) 688-2561 | mario_orso@dot.ca.gov | |
Right of Way Phase |
Caltrans | Mario Orso | (619) 688-2561 | mario_orso@dot.ca.gov | |
Construction Phase |
Caltrans | Mario Orso | (619) 688-2561 | mario_orso@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$1,150 | $-789 | $361 | ||||
Ports Inf, Sec, & AQ |
$1,180 | $170 | $1,350 | ||||
Non-bond Funding | |||||||
Local** |
$930 | $-910 | $20 | ||||
Total**** | $3,260 | $-1,529 | $1,731 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$100 | $431 | $531 | $0 | $0 | $531 | |
Design(PS&E) |
$180 | $120 | $300 | $0 | $0 | $300 | |
Right of Way |
$680 | $-643 | $37 | $0 | $0 | $37 | |
Construction |
$2,300 | $-1,437 | $863 | $0 | $0 | $863 | |
Total* | $3,260 | $-1,529 | $1,731 | $0 | $0 | $1,731 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/02/2008 08/05/2010 |
|
07/02/2008 08/05/2010 |
100 | 08/05/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/06/2010 12/29/2011 |
08/10/2011 |
08/06/2010 02/29/2012 |
100 | 08/06/2010 02/29/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/06/2010 12/29/2011 |
|
08/06/2010 12/29/2011 |
100 | 08/06/2010 12/29/2011 |
0 0 |
Begin Construction Phase
End Construction Phase |
06/14/2012 11/07/2013 |
|
06/14/2012 11/07/2013 |
100 | 06/21/2012 04/11/2014 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
05/07/2014 11/07/2014 |
|
05/07/2014 11/07/2014 |
50 | 05/07/2014 11/07/2014 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,330,000 |
Current Approved: |
$361,000 |
Actual Expenditures: |
$342,000 |
Status as of December 31, 2023.