FRANKLIN BLVD AND ELK GROVE BLVD TRAFFIC SIGNAL IMPROVEMENTS

Description: FRANKLIN BLVD AND ELK GROVE BLVD TRAFFIC SIGNAL IMPROVEMENTS

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City Elk Grove
Zip Code 95758
 
Senate District
01, 05
Assembly District 10, 15
Congressional District 03, 05
 
Caltrans District
03
 
 
County/State Route Sacramento N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in System Reliability        
Lane Miles Added (Mixed)        
Peak Period Time Savings (minutes)        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Elk Grove Diane Nguyen (916) 478-2232   dnguyen@elkgrovecity.org
Design (PS&E) Phase
Elk Grove Diane Nguyen (916) 478-2232   dnguyen@elkgrovecity.org
Right of Way Phase
Elk Grove Gary Grunwald (916) 478-2236   ggrunwald@elkgrovecity.org
Construction Phase
Elk Grove Gary Grunwald (916) 478-2236   ggrunwald@elkgrovecity.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$988 $-452 $536
Non-bond Funding
Local**
$3,027 $-452 $2,575
 
Total**** $4,015 $-904 $3,111

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$615 $0 $615 $615 $615 $0
Design(PS&E)
$1,000 $0 $1,000 $1,000 $1,000 $0
Right of Way
$424 $0 $424 $424 $424 $0
Construction
$1,976 $-904 $1,072 $1,064 $1,064 $8
 
Total* $4,015 $-904 $3,111 $3,103 $3,103 $8

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

04/01/2006 
 

 
09/01/2004 

10/01/2005 
100  09/01/2004 

10/01/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

07/01/2009 
 

 
10/01/2007 

03/01/2009 
100  10/01/2007 

03/01/2009 


Begin Right of Way Phase

End Right of Way Phase
04/01/2006 

07/01/2009 
 

 
12/01/2005 

06/01/2009 
100  12/01/2005 

06/01/2009 


Begin Construction Phase

End Construction Phase
10/01/2009 

01/01/2010 
03/29/2010 

03/29/2010 
04/01/2010 

12/01/2010 
100  04/01/2010 

12/08/2010 


Begin Closeout Phase

End Closeout Phase
10/01/2010 

03/01/2011 
03/29/2010 

 
01/01/2011 

03/01/2011 
100  01/01/2011 

05/01/2011 


-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in System Reliability
Lane Miles Added (Mixed)
Peak Period Time Savings (minutes)
Reduced Emissions

Bond Funding Cost
Adopted:
$988,000
Current Approved:
$988,000
Actual Expenditures:
$532,198

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle