Caltrans Logo

GREENFIELD AVE. EXTENSION - DELLA ST TO 12 AVE

Description: GREENFIELD AVE. EXTENSION - DELLA ST TO 12 AVE

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings County
City Hanford
Zip Code 93230
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  0.5      
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Hanford Lou Camara 559-585-2567   lcamara@ci.hanford.ca.us
Design (PS&E) Phase
Hanford Lou Camara 559-585-2567   lcamara@ci.hanford.ca.us
Right of Way Phase
Hanford Lou Camara 559-585-2567   lcamara@ci.hanford.ca.us
Construction Phase
Hanford Lou Camara 559-585-2567   lcamara@ci.hanford.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$250 $0 $250
Non-bond Funding
Local**
$645 $-264 $381
 
Total**** $895 $-264 $631

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$70 $-39 $31 $31 $31 $-0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$825 $-225 $600 $609 $609 $-9
 
Total* $895 $-264 $631 $640 $640 $-9

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2009 

06/16/2009 
 

 
02/01/2009 

06/16/2009 
100  02/01/2009 

06/16/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

03/01/2009 
 

03/01/2010 
07/01/2007 

04/15/2010 
100  07/01/2007 

04/15/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
07/15/2009 

11/15/2009 
03/01/2010 

03/01/2011 
08/01/2010 

05/02/2011 
100  08/01/2010 

06/07/2011 


-1 
Begin Closeout Phase

End Closeout Phase
11/01/2010 

12/01/2010 
03/01/2011 

 
05/02/2011 

07/04/2011 
100  05/02/2011 

09/30/2011 


-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 0.5
Reduced Emissions

Bond Funding Cost
Adopted:
$250,000
Current Approved:
$250,000
Actual Expenditures:
$184,495

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle