POINT VIEW DRIVE EXTENSION

Description: POINT VIEW DRIVE EXTENSION

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado County
City Placerville
Zip Code 95667
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in System Reliability        
Increase in Throughput        
Peak Period Time Savings (minutes)        
Ramp Widenings        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Placerville Nate Stong (530) 642-5250   nstong@cityofplacerville.org
Right of Way Phase
Placerville Nate Stong (530) 642-5250   nstong@cityofplacerville.org
Construction Phase
Placerville Nate Stong (530) 642-5250   nstong@cityofplacerville.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$750 $0 $750
Non-bond Funding
Local**
$2,410 $20 $2,430
 
Total**** $3,160 $20 $3,180

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$300 $0 $300 $300 $300 $0
Design(PS&E)
$330 $20 $350 $350 $350 $0
Right of Way
$75 $0 $75 $75 $75 $0
Construction
$2,455 $0 $2,455 $1,674 $1,674 $781
 
Total* $3,160 $20 $3,180 $2,399 $2,399 $781

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2003 

09/13/2007 
 

09/13/2007 
01/01/2003 

09/13/2007 
100  01/01/2003 

09/13/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/11/2003 

04/10/2009 
 

 
02/11/2003 

12/22/2010 
100  02/11/2003 

02/09/2011 


-2 
Begin Right of Way Phase

End Right of Way Phase
05/01/2006 

05/26/2009 
 

 
05/01/2006 

01/28/2011 
100  05/01/2006 

01/28/2011 


Begin Construction Phase

End Construction Phase
10/27/2009 

10/15/2011 
 

 
04/05/2011 

10/15/2011 
100  06/01/2011 

01/10/2012 
-2 

-3 
Begin Closeout Phase

End Closeout Phase
10/27/2009 

01/15/2012 
 

 
11/01/2011 

01/15/2012 
100  01/10/2012 

02/14/2012 
-2 

-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in System Reliability
Increase in Throughput
Peak Period Time Savings (minutes)
Ramp Widenings
Reduced Emissions

Bond Funding Cost
Adopted:
$750,000
Current Approved:
$750,000
Actual Expenditures:
$750,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle