MISSION BLVD GAP CLOSURE PROJECT

Description: MISSION BLVD GAP CLOSURE PROJECT

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Amador
City Jackson
Zip Code 95642
 
Senate District
01
Assembly District 10
Congressional District 03
 
Caltrans District
10
 
 
County/State Route Amador NA
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in Throughput        
Lane Miles Added (Mixed)        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Amador County Charles Field (209) 267-2282   charles@actc-amador.org
Design (PS&E) Phase
Amador County Charles Field (209) 267-2282   charles@actc-amador.org
Right of Way Phase
Amador County Charles Field (209) 267-2282   charles@actc-amador.org
Construction Phase
Amador County Charles Field (209) 267-2282   charles@actc-amador.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$800 $-386 $414
Non-bond Funding
Local**
$1,155 $-324 $831
 
Total**** $1,955 $-711 $1,244

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$50 $0 $50 $50 $50 $0
Design(PS&E)
$130 $-21 $109 $109 $109 $0
Right of Way
$175 $83 $258 $258 $258 $0
Construction
$1,600 $-773 $827 $846 $846 $-18
 
Total* $1,955 $-711 $1,244 $1,263 $1,263 $-18

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2002 

06/01/2003 
 

 
02/01/2002 

06/01/2003 
100  02/01/2002 

06/01/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/03/2003 

01/01/2009 
 

 
02/03/2003 

01/01/2009 
100  02/03/2003 

01/01/2009 


Begin Right of Way Phase

End Right of Way Phase
07/01/2008 

05/01/2009 
 

 
07/01/2008 

05/01/2009 
100  07/01/2008 

05/01/2009 


Begin Construction Phase

End Construction Phase
07/01/2009 

12/01/2009 
03/01/2010 

03/01/2010 
04/19/2010 

11/01/2010 
100  04/19/2010 

01/27/2011 


-3 
Begin Closeout Phase

End Closeout Phase
02/01/2010 

11/30/2010 
03/01/2010 

 
09/03/2010 

11/30/2010 
100  01/28/2011 

03/18/2011 
-5 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in Throughput
Lane Miles Added (Mixed)
Reduced Emissions

Bond Funding Cost
Adopted:
$800,000
Current Approved:
$800,000
Actual Expenditures:
$422,843

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle