Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
11TH AVE WIDENING/ RECONSTRUCTION PROJECT - HUME AVE TO HOUSTON AVE |
Description: 11TH AVE WIDENING/ RECONSTRUCTION PROJECT - HUME AVE TO HOUSTON AVE
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings County |
City | Hanford |
Zip Code | 93230 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added | ||
Lane Miles Added (Mixed) | ||
Rehabilitated Lane Miles (miles) | 2 | |
XX | N |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Hanford | Lou Camara | 555-585-2567 | lcamara@ci.hanford.ca.us | |
Design (PS&E) Phase |
Hanford | Lou Camara | 555-585-2567 | lcamara@ci.hanford.ca.us | |
Right of Way Phase |
Hanford | Lou Camara | 555-585-2567 | lcamara@ci.handfor.ca.us | |
Construction Phase |
Hanford | Lou Camara | 559-585-2567 | lcamara@ci.hanford.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$500 | $0 | $500 | ||||
Non-bond Funding | |||||||
Local** |
$820 | $0 | $820 | ||||
Total**** | $1,320 | $0 | $1,320 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $98 | $98 | $-98 | |
Right of Way |
$0 | $0 | $0 | $10 | $10 | $-10 | |
Construction |
$1,320 | $0 | $1,320 | $1,045 | $1,045 | $275 | |
Total* | $1,320 | $0 | $1,320 | $1,154 | $1,154 | $166 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/01/2007 06/15/2007 |
03/01/2010 03/01/2010 |
08/01/2009 09/30/2009 |
100 | 08/01/2009 09/30/2009 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 07/01/2009 |
03/01/2010 |
07/01/2008 02/01/2010 |
100 | 07/01/2008 02/01/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/01/2009 09/01/2009 |
03/01/2010 |
03/01/2009 10/20/2009 |
100 | 03/01/2009 10/20/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/15/2009 05/01/2010 |
03/01/2010 03/01/2010 |
06/28/2010 10/31/2010 |
100 | 06/28/2010 04/05/2011 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
07/01/2010 12/01/2010 |
03/01/2001 |
11/01/2010 12/01/2010 |
100 | 04/06/2011 10/06/2011 |
-5 -10 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added | ||
Lane Miles Added (Mixed) | ||
Rehabilitated Lane Miles (miles) | 2 | |
XX | N |
Bond Funding Cost | |
---|---|
Adopted: |
$500,000 |
Current Approved: |
$500,000 |
Actual Expenditures: |
$395,898 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle