DUROCK ROAD/BUSINESS DRIVE INTERSECTION

Description: DUROCK ROAD/BUSINESS DRIVE INTERSECTION

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado County
City
Zip Code 95682
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 50
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
El Dorado County Chuck Pazzi (916) 358-3653   chuck.pazzi@edcgov.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$710 $0 $710
Non-bond Funding
Local**
$1,030 $0 $1,030
 
Total**** $1,740 $0 $1,740

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$78 $0 $78 $86 $86 $-8
Design(PS&E)
$128 $0 $128 $526 $526 $-398
Right of Way
$94 $0 $94 $140 $140 $-46
Construction
$1,440 $0 $1,440 $1,295 $1,295 $145
 
Total* $1,740 $0 $1,740 $2,047 $2,047 $-307

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/15/2007 

12/10/2009 
 

 
04/15/2007 

12/10/2009 
100  04/15/2007 

12/10/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/20/2007 

07/29/2009 
 

 
02/20/2007 

08/24/2010 
100  02/20/2007 

08/24/2010 


Begin Right of Way Phase

End Right of Way Phase
04/01/2008 

03/01/2009 
 

 
04/01/2008 

07/20/2009 
100  04/01/2008 

07/20/2009 


Begin Construction Phase

End Construction Phase
04/29/2010 

11/17/2010 
 

 
08/24/2010 

02/18/2011 
100  08/24/2010 

09/13/2011 


-7 
Begin Closeout Phase

End Closeout Phase
02/01/2011 

02/01/2011 
 

 
02/18/2011 

05/18/2011 
100  09/13/2011 

07/31/2012 
-7 

-15 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Reduced Emissions

Bond Funding Cost
Adopted:
$710,000
Current Approved:
$710,000
Actual Expenditures:
$647,403

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle