SILVA VALLEY PARKWAY WIDENING

Description: SILVA VALLEY PARKWAY WIDENING

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado County
City
Zip Code 95667
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Increase in Throughput        
Peak Period Time Savings (minutes)        
Reduced Emissions        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
El Dorado County Paul Hom (916) 358-3678   phom@edcgov.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$993 $0 $993
Non-bond Funding
Local**
$1,742 $-286 $1,456
 
Total**** $2,736 $-286 $2,449

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $11 $11 $13 $13 $-1
Design(PS&E)
$355 $87 $442 $407 $407 $35
Right of Way
$15 $-5 $10 $14 $14 $-4
Construction
$2,366 $-380 $1,986 $731 $731 $1,255
 
Total* $2,736 $-286 $2,449 $1,164 $1,164 $1,285

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2008 

05/01/2009 
 

 
11/01/2008 

05/01/2009 
100  11/01/2008 

05/01/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2009 

12/01/2009 
 

 
05/01/2009 

12/01/2009 
100  05/01/2009 

10/25/2010 


-11 
Begin Right of Way Phase

End Right of Way Phase
11/15/2009 

08/10/2010 
 

 
11/15/2009 

08/10/2010 
100  11/15/2009 

10/29/2010 


-3 
Begin Construction Phase

End Construction Phase
01/01/2010 

04/01/2011 
 

 
01/01/2010 

06/30/2011 
100  10/29/2010 

04/13/2012 
-10 

-10 
Begin Closeout Phase

End Closeout Phase
06/30/2011 

08/31/2011 
 

 
06/30/2011 

08/31/2011 
100  04/13/2012 

10/26/2012 
-10 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Increase in Throughput
Peak Period Time Savings (minutes)
Reduced Emissions
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$993,000
Current Approved:
$993,000
Actual Expenditures:
$365,370

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle