FAIRVIEW/BERKELY TRAFFIC SIGNAL INSTALLATION

Description: FAIRVIEW/BERKELY TRAFFIC SIGNAL INSTALLATION

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City Goleta
Zip Code 93117
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase Safety        
Increase in Throughput        
Peak Period Time Savings (minutes)        
XX  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Goleta ROSEMARIE GAGLIONE 808-961-7569   RGAGLIONE@CITYOFGOLETA.ORG
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$150 $0 $150
Non-bond Funding
Local**
$166 $0 $166
 
Total**** $316 $0 $316

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $19 $19 $-4
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$300 $0 $300 $203 $203 $97
 
Total* $316 $0 $316 $223 $223 $92

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/19/2007 

12/19/2007 
 

 
12/19/2007 

12/19/2007 
100  12/19/2007 

12/19/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/15/2009 

10/15/2009 
 

 
03/15/2010 

09/04/2010 
100  03/15/2010 

09/04/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/30/2009 

01/15/2010 
03/01/2011 

03/01/2011 
02/07/2011 

04/14/2011 
100  02/07/2011 

04/14/2011 


Begin Closeout Phase

End Closeout Phase
02/15/2010 

02/16/2011 
03/01/2011 

 
04/15/2011 

05/31/2011 
100  04/15/2011 

01/23/2012 


-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase Safety
Increase in Throughput
Peak Period Time Savings (minutes)
XX N

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$150,000
Actual Expenditures:
$101,650

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle