GOLF CENTER PARKWAY REHABILITATION |
Description: GOLF CENTER PARKWAY REHABILITATION
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Indio |
Zip Code | 92201 |
Senate District |
37 |
Assembly District | 80 |
Congressional District | 45 |
Caltrans District |
08 |
County/State Route | Riverside N/A |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Improve Roadway | ||
Increase in Throughput | ||
Rehabilitated Lane Miles (miles) | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Indio | Tom Rafferty | (760) 391-4017 | trafferty@indio.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$433 | $0 | $433 | ||||
Non-bond Funding | |||||||
Local** |
$2,967 | $0 | $2,967 | ||||
Total**** | $3,400 | $0 | $3,400 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$200 | $0 | $200 | $200 | $200 | $0 | |
Design(PS&E) |
$200 | $0 | $200 | $200 | $200 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,000 | $0 | $3,000 | $2,026 | $2,026 | $974 | |
Total* | $3,400 | $0 | $3,400 | $2,426 | $2,426 | $974 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/06/2009 09/08/2009 |
|
08/06/2009 09/08/2009 |
100 | 08/06/2009 08/06/2009 |
0 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2009 09/15/2009 |
|
05/01/2009 09/15/2009 |
100 | 05/01/2009 09/15/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/22/2010 07/12/2010 |
|
02/22/2010 07/12/2010 |
100 | 02/22/2010 07/12/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/12/2010 12/13/2010 |
|
07/12/2010 12/13/2010 |
100 | 07/12/2010 12/13/2010 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Improve Roadway | ||
Increase in Throughput | ||
Rehabilitated Lane Miles (miles) | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$433,000 |
Current Approved: |
$433,000 |
Actual Expenditures: |
$433,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle