GOLF CENTER PARKWAY REHABILITATION

Description: GOLF CENTER PARKWAY REHABILITATION

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City Indio
Zip Code 92201
 
Senate District
37
Assembly District 80
Congressional District 45
 
Caltrans District
08
 
 
County/State Route Riverside N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Improve Roadway        
Increase in Throughput        
Rehabilitated Lane Miles (miles)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Indio Tom Rafferty (760) 391-4017   trafferty@indio.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$433 $0 $433
Non-bond Funding
Local**
$2,967 $0 $2,967
 
Total**** $3,400 $0 $3,400

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$200 $0 $200 $200 $200 $0
Design(PS&E)
$200 $0 $200 $200 $200 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,000 $0 $3,000 $2,026 $2,026 $974
 
Total* $3,400 $0 $3,400 $2,426 $2,426 $974

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/06/2009 

09/08/2009 
 

 
08/06/2009 

09/08/2009 
100  08/06/2009 

08/06/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2009 

09/15/2009 
 

 
05/01/2009 

09/15/2009 
100  05/01/2009 

09/15/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/22/2010 

07/12/2010 
 

 
02/22/2010 

07/12/2010 
100  02/22/2010 

07/12/2010 


Begin Closeout Phase

End Closeout Phase
07/12/2010 

12/13/2010 
 

 
07/12/2010 

12/13/2010 
100  07/12/2010 

12/13/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Improve Roadway
Increase in Throughput
Rehabilitated Lane Miles (miles) 2

Bond Funding Cost
Adopted:
$433,000
Current Approved:
$433,000
Actual Expenditures:
$433,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle