NEVADA CITY PAVING |
Description: NEVADA CITY PAVING
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Nevada County |
City | Nevada City |
Zip Code | 95959 |
Senate District |
04 |
Assembly District | 03 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | Nevada 0 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 0.25 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Nevada City | William J. Falconi | (530) 265-2496 | corey.shaver@co.nevada.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$31 | $0 | $31 | ||||
Non-bond Funding | |||||||
Local** |
$34 | $-3 | $31 | ||||
Total**** | $65 | $-3 | $62 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$65 | $-3 | $62 | $75 | $75 | $-13 | |
Total* | $65 | $-3 | $62 | $75 | $75 | $-13 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2010 01/19/2010 |
02/10/2010 |
01/01/2010 04/27/2010 |
100 | 01/01/2010 04/27/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/28/2010 02/19/2010 |
02/10/2010 |
01/28/2010 04/28/2010 |
100 | 01/28/2010 04/28/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2009 07/01/2009 |
02/10/2010 02/10/2010 |
05/02/2011 08/26/2011 |
100 | 06/08/2011 06/14/2011 |
-1 2 |
Begin Closeout Phase
End Closeout Phase |
08/01/2009 10/29/2010 |
02/10/2010 |
08/26/2011 09/30/2011 |
100 | 06/15/2011 12/16/2011 |
2 -3 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 0.25 |
Bond Funding Cost | |
---|---|
Adopted: |
$31,000 |
Current Approved: |
$31,000 |
Actual Expenditures: |
$31,000 |
Status as of December 31, 2023.