NEVADA CITY PAVING

Description: NEVADA CITY PAVING

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada County
City Nevada City
Zip Code 95959
 
Senate District
04
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Nevada 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)  0.25      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Nevada City William J. Falconi (530) 265-2496   corey.shaver@co.nevada.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$31 $0 $31
Non-bond Funding
Local**
$34 $-3 $31
 
Total**** $65 $-3 $62

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$65 $-3 $62 $75 $75 $-13
 
Total* $65 $-3 $62 $75 $75 $-13

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2010 

01/19/2010 
 

02/10/2010 
01/01/2010 

04/27/2010 
100  01/01/2010 

04/27/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/28/2010 

02/19/2010 
 

02/10/2010 
01/28/2010 

04/28/2010 
100  01/28/2010 

04/28/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2009 

07/01/2009 
02/10/2010 

02/10/2010 
05/02/2011 

08/26/2011 
100  06/08/2011 

06/14/2011 
-1 

Begin Closeout Phase

End Closeout Phase
08/01/2009 

10/29/2010 
02/10/2010 

 
08/26/2011 

09/30/2011 
100  06/15/2011 

12/16/2011 


-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles) 0.25

Bond Funding Cost
Adopted:
$31,000
Current Approved:
$31,000
Actual Expenditures:
$31,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle