2010 ANNUAL SLURRY SEAL PROJECT

Description: 2010 ANNUAL SLURRY SEAL PROJECT

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada County
City Truckee
Zip Code 96161
 
Senate District
01
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Nevada 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Truckee Becky Bucar (530) 582-2932   bbucar@townoftruckee.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$81 $82 $163
Non-bond Funding
State/Federal*
$0 $99 $99
Local**
$526 $-283 $243
 
Total**** $608 $-102 $506

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$608 $-102 $506 $506 $506 $0
 
Total* $608 $-102 $506 $506 $506 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/15/2010 

03/15/2010 
 

 
02/15/2010 

03/15/2010 
100  03/01/2010 

04/15/2010 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/15/2010 

05/30/2010 
 

 
03/05/2010 

05/30/2010 
100  03/15/2010 

06/09/2010 


Begin Right of Way Phase

End Right of Way Phase
05/30/2010 

05/30/2010 
 

 
05/30/2010 

05/30/2010 
100  05/30/2010 

05/30/2010 


Begin Construction Phase

End Construction Phase
06/01/2010 

10/30/2010 
 

 
06/01/2010 

10/30/2010 
100  07/29/2010 

10/08/2010 
-2 

Begin Closeout Phase

End Closeout Phase
12/30/2010 

01/31/2011 
 

 
12/30/2010 

01/31/2011 
100  10/08/2010 

04/29/2011 


-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$81,000
Current Approved:
$163,000
Actual Expenditures:
$163,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle