MAGNOLIA AVE AND NEECE STREET SIGNAL |
Description: MAGNOLIA AVE AND NEECE STREET SIGNAL
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Riverside |
Zip Code | 92879 |
Senate District |
37 |
Assembly District | 71 |
Congressional District | 44 |
Caltrans District |
08 |
County/State Route | Riverside 0 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Riverside County | Dowling Tsai | (951) 955-8562 | dtsai@rctlma.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$150 | $0 | $150 | ||||
Non-bond Funding | |||||||
Local** |
$631 | $815 | $1,446 | ||||
Total**** | $781 | $815 | $1,596 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1 | $0 | $1 | $1 | $1 | $0 | |
Design(PS&E) |
$100 | $75 | $175 | $175 | $175 | $0 | |
Right of Way |
$60 | $740 | $800 | $61 | $61 | $739 | |
Construction |
$620 | $0 | $620 | $666 | $666 | $-46 | |
Total* | $781 | $815 | $1,596 | $903 | $903 | $693 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2007 02/28/2008 |
|
12/01/2007 02/28/2008 |
100 | 12/01/2007 02/28/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2007 12/31/2009 |
03/01/2011 |
01/01/2007 05/31/2011 |
100 | 01/01/2007 05/31/2011 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2009 04/30/2010 |
03/01/2011 |
04/01/2009 05/31/2011 |
100 | 04/01/2009 03/27/2012 |
0 -10 |
Begin Construction Phase
End Construction Phase |
09/01/2010 11/30/2010 |
|
08/01/2011 03/01/2012 |
100 | 06/26/2012 11/05/2013 |
-11 -20 |
Begin Closeout Phase
End Closeout Phase |
02/28/2011 08/15/2012 |
|
03/15/2012 08/15/2012 |
100 | 11/06/2013 03/18/2014 |
-20 -19 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput |
Bond Funding Cost | |
---|---|
Adopted: |
$150,000 |
Current Approved: |
$150,000 |
Actual Expenditures: |
$150,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle