MAGNOLIA AVE AND NEECE STREET SIGNAL

Description: MAGNOLIA AVE AND NEECE STREET SIGNAL

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City Riverside
Zip Code 92879
 
Senate District
37
Assembly District 71
Congressional District 44
 
Caltrans District
08
 
 
County/State Route Riverside 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Riverside County Dowling Tsai (951) 955-8562   dtsai@rctlma.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$150 $0 $150
Non-bond Funding
Local**
$631 $815 $1,446
 
Total**** $781 $815 $1,596

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $0 $1 $1 $1 $0
Design(PS&E)
$100 $75 $175 $175 $175 $0
Right of Way
$60 $740 $800 $61 $61 $739
Construction
$620 $0 $620 $666 $666 $-46
 
Total* $781 $815 $1,596 $903 $903 $693

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2007 

02/28/2008 
 

 
12/01/2007 

02/28/2008 
100  12/01/2007 

02/28/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2007 

12/31/2009 
 

03/01/2011 
01/01/2007 

05/31/2011 
100  01/01/2007 

05/31/2011 


Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

04/30/2010 
 

03/01/2011 
04/01/2009 

05/31/2011 
100  04/01/2009 

03/27/2012 


-10 
Begin Construction Phase

End Construction Phase
09/01/2010 

11/30/2010 
 

 
08/01/2011 

03/01/2012 
100  06/26/2012 

11/05/2013 
-11 

-20 
Begin Closeout Phase

End Closeout Phase
02/28/2011 

08/15/2012 
 

 
03/15/2012 

08/15/2012 
100  11/06/2013 

03/18/2014 
-20 

-19 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$150,000
Actual Expenditures:
$150,000

 

Status as of December 31, 2023.