Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
VARIOUS STREETS - 3RD AND ADA IMPROVEMENTS |
Description: VARIOUS STREETS - 3RD AND ADA IMPROVEMENTS
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera County |
City | Madera |
Zip Code | 93637 |
Senate District |
12 |
Assembly District | 29 |
Congressional District | 19 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement lane Miles | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Madera | Les Jorgensen | 559-661-5429 | ljorgensen@cityofmadera.com | |
Design (PS&E) Phase |
Madera | Les Jorgensen | 559-661-5429 | ljorgensen@cityofmadera.com | |
Right of Way Phase |
Madera | Les Jorgensen | 559-661-5429 | ljorgensen@cityofmadera.com | |
Construction Phase |
Madera | Les Jorgensen | 559-661-5429 | ljorgensen@cityofmadera.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$356 | $0 | $356 | ||||
Non-bond Funding | |||||||
Local** |
$615 | $-444 | $171 | ||||
Total**** | $971 | $-444 | $527 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$5 | $0 | $5 | $5 | $5 | $0 | |
Design(PS&E) |
$15 | $0 | $15 | $15 | $15 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$951 | $-444 | $507 | $347 | $347 | $160 | |
Total* | $971 | $-444 | $527 | $367 | $367 | $160 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/05/2009 08/19/2009 |
|
05/05/2009 08/19/2009 |
100 | 05/05/2009 08/19/2009 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/20/2009 07/17/2009 |
|
04/20/2009 07/17/2009 |
100 | 04/20/2009 07/17/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/07/2010 10/30/2010 |
|
10/18/2010 05/31/2011 |
100 | 10/06/2010 12/21/2011 |
0 -7 |
Begin Closeout Phase
End Closeout Phase |
10/30/2010 10/30/2011 |
|
09/05/2011 04/24/2012 |
100 | 01/16/2012 09/28/2012 |
-4 -5 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement lane Miles | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$356,000 |
Current Approved: |
$150,000 |
Actual Expenditures: |
$150,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle