VARIOUS STREETS - 3RD AND ADA IMPROVEMENTS

Description: VARIOUS STREETS - 3RD AND ADA IMPROVEMENTS

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera County
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Pavement lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Madera Les Jorgensen 559-661-5429   ljorgensen@cityofmadera.com
Design (PS&E) Phase
Madera Les Jorgensen 559-661-5429   ljorgensen@cityofmadera.com
Right of Way Phase
Madera Les Jorgensen 559-661-5429   ljorgensen@cityofmadera.com
Construction Phase
Madera Les Jorgensen 559-661-5429   ljorgensen@cityofmadera.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$356 $0 $356
Non-bond Funding
Local**
$615 $-444 $171
 
Total**** $971 $-444 $527

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $0 $5 $5 $5 $0
Design(PS&E)
$15 $0 $15 $15 $15 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$951 $-444 $507 $347 $347 $160
 
Total* $971 $-444 $527 $367 $367 $160

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/05/2009 

08/19/2009 
 

 
05/05/2009 

08/19/2009 
100  05/05/2009 

08/19/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/20/2009 

07/17/2009 
 

 
04/20/2009 

07/17/2009 
100  04/20/2009 

07/17/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/07/2010 

10/30/2010 
 

 
10/18/2010 

05/31/2011 
100  10/06/2010 

12/21/2011 


-7 
Begin Closeout Phase

End Closeout Phase
10/30/2010 

10/30/2011 
 

 
09/05/2011 

04/24/2012 
100  01/16/2012 

09/28/2012 
-4 

-5 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$356,000
Current Approved:
$150,000
Actual Expenditures:
$150,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle