VARIOUS STREETS 3RD AND ADA IMPROVEMENTS |
Description: VARIOUS STREETS 3RD AND ADA IMPROVEMENTS
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera County |
City | Madera |
Zip Code | 93637 |
Senate District |
12 |
Assembly District | 29 |
Congressional District | 19 |
Caltrans District |
06 |
County/State Route | Madera 0 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Pavemnet Lanes Miles | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Madera | Jose Aguilar | 559-661-5423 | jaguilar@cityofmadera.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$216 | $-79 | $137 | ||||
Non-bond Funding | |||||||
Local** |
$228 | $0 | $228 | ||||
Total**** | $444 | $-79 | $365 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $3 | $3 | $-3 | |
Design(PS&E) |
$10 | $0 | $10 | $7 | $7 | $3 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$434 | $-79 | $355 | $242 | $242 | $113 | |
Total* | $444 | $-79 | $365 | $252 | $252 | $113 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2009 11/01/2009 |
|
08/01/2009 11/01/2009 |
100 | 06/23/2009 08/19/2009 |
1 2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2009 12/01/2009 |
|
08/01/2009 12/01/2009 |
100 | 08/01/2009 12/01/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2009 07/01/2009 |
|
06/15/2011 08/15/2011 |
100 | 07/06/2011 12/21/2011 |
-1 -4 |
Begin Closeout Phase
End Closeout Phase |
09/30/2009 07/31/2011 |
|
02/28/2012 08/30/2012 |
100 | 02/28/2012 08/30/2012 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Pavemnet Lanes Miles | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$216,000 |
Current Approved: |
$137,000 |
Actual Expenditures: |
$121,188 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle