Caltrans Logo

VARIOUS STREETS 3RD AND ADA IMPROVEMENTS

Description: VARIOUS STREETS 3RD AND ADA IMPROVEMENTS

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera County
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
 
County/State Route Madera 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Pavemnet Lanes Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Madera Jose Aguilar 559-661-5423   jaguilar@cityofmadera.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$216 $-79 $137
Non-bond Funding
Local**
$228 $0 $228
 
Total**** $444 $-79 $365

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $3 $3 $-3
Design(PS&E)
$10 $0 $10 $7 $7 $3
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$434 $-79 $355 $242 $242 $113
 
Total* $444 $-79 $365 $252 $252 $113

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2009 

11/01/2009 
 

 
08/01/2009 

11/01/2009 
100  06/23/2009 

08/19/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2009 

12/01/2009 
 

 
08/01/2009 

12/01/2009 
100  08/01/2009 

12/01/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2009 

07/01/2009 
 

 
06/15/2011 

08/15/2011 
100  07/06/2011 

12/21/2011 
-1 

-4 
Begin Closeout Phase

End Closeout Phase
09/30/2009 

07/31/2011 
 

 
02/28/2012 

08/30/2012 
100  02/28/2012 

08/30/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Pavemnet Lanes Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$216,000
Current Approved:
$137,000
Actual Expenditures:
$121,188

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle