ROAD 200 RECONSTRUCTION & WIDENING

Description: ROAD 200 RECONSTRUCTION & WIDENING

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera County
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
 
County/State Route Madera 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Increase in System Reliablility        
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Madera County Jared Carter 559-675-7811   jcarter@madera-county.com
Design (PS&E) Phase
Madera County Jared Carter 559-675-7811   jcarter@madera-county.com
Right of Way Phase
Madera County Jared Carter 559-675-7811   jcarter@madera-county.com
Construction Phase
Madera County Jared Carter 559-675-7811   jcarter@madera-county.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$544 $-173 $371
Non-bond Funding
Local**
$5,975 $-5,152 $824
 
Total**** $6,519 $-5,324 $1,194

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $325 $325 $-325
Design(PS&E)
$500 $-442 $58 $575 $575 $-518
Right of Way
$395 $0 $395 $395 $395 $0
Construction
$5,624 $-4,882 $742 $726 $726 $16
 
Total* $6,519 $-5,324 $1,194 $2,021 $2,021 $-827

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2008 

09/12/2009 
 

 
09/01/2008 

05/30/2011 
100  09/01/2008 

02/28/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/03/2007 

01/06/2010 
 

 
04/03/2007 

06/01/2011 
100  04/03/2007 

03/07/2011 


Begin Right of Way Phase

End Right of Way Phase
02/15/2010 

09/12/2010 
 

 
02/15/2010 

03/05/2010 
100  02/15/2010 

03/05/2010 


Begin Construction Phase

End Construction Phase
06/15/2010 

12/13/2010 
03/01/2011 

03/01/2011 
06/01/2011 

11/30/2011 
100  07/11/2011 

01/24/2012 
-1 

-2 
Begin Closeout Phase

End Closeout Phase
03/04/2011 

06/30/2011 
03/01/2011 

 
12/01/2011 

01/31/2012 
100  01/30/2012 

04/30/2012 
-2 

-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliablility
Increase in Throughput

Bond Funding Cost
Adopted:
$544,000
Current Approved:
$371,000
Actual Expenditures:
$363,075

 

Status as of December 31, 2023.