ROAD 200 RECONSTRUCTION & WIDENING |
Description: ROAD 200 RECONSTRUCTION & WIDENING
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera County |
City | Madera |
Zip Code | 93637 |
Senate District |
12 |
Assembly District | 29 |
Congressional District | 19 |
Caltrans District |
06 |
County/State Route | Madera 0 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliablility | ||
Increase in Throughput |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Madera County | Jared Carter | 559-675-7811 | jcarter@madera-county.com | |
Design (PS&E) Phase |
Madera County | Jared Carter | 559-675-7811 | jcarter@madera-county.com | |
Right of Way Phase |
Madera County | Jared Carter | 559-675-7811 | jcarter@madera-county.com | |
Construction Phase |
Madera County | Jared Carter | 559-675-7811 | jcarter@madera-county.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$544 | $-173 | $371 | ||||
Non-bond Funding | |||||||
Local** |
$5,975 | $-5,152 | $824 | ||||
Total**** | $6,519 | $-5,324 | $1,194 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $325 | $325 | $-325 | |
Design(PS&E) |
$500 | $-442 | $58 | $575 | $575 | $-518 | |
Right of Way |
$395 | $0 | $395 | $395 | $395 | $0 | |
Construction |
$5,624 | $-4,882 | $742 | $726 | $726 | $16 | |
Total* | $6,519 | $-5,324 | $1,194 | $2,021 | $2,021 | $-827 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/2008 09/12/2009 |
|
09/01/2008 05/30/2011 |
100 | 09/01/2008 02/28/2011 |
0 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/03/2007 01/06/2010 |
|
04/03/2007 06/01/2011 |
100 | 04/03/2007 03/07/2011 |
0 3 |
Begin Right of Way Phase
End Right of Way Phase |
02/15/2010 09/12/2010 |
|
02/15/2010 03/05/2010 |
100 | 02/15/2010 03/05/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
06/15/2010 12/13/2010 |
03/01/2011 03/01/2011 |
06/01/2011 11/30/2011 |
100 | 07/11/2011 01/24/2012 |
-1 -2 |
Begin Closeout Phase
End Closeout Phase |
03/04/2011 06/30/2011 |
03/01/2011 |
12/01/2011 01/31/2012 |
100 | 01/30/2012 04/30/2012 |
-2 -3 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliablility | ||
Increase in Throughput |
Bond Funding Cost | |
---|---|
Adopted: |
$544,000 |
Current Approved: |
$371,000 |
Actual Expenditures: |
$363,075 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle