BULLARD/LOCAN

Description: BULLARD/LOCAN

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno County
City Clovis
Zip Code 93612
 
Senate District
14
Assembly District 29
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in System Reliability        
Increase in Throughput        
Lane Miles Added (Mixed)        
Pavement Lane Miles        
Peak Period Time Savings (minutes)        
Reduced Emissions        
Reduced Operating/Maintenance Cost        
Rehabilitated Lane Miles (miles)        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Clovis Ryan Burnett (559)324-2336   ryanb@cityofclovis.com
Design (PS&E) Phase
Clovis Mike Harrison (559) 324-2365   mikeh@cityofclovis.com
Right of Way Phase
Clovis Ryan Burnett (559) 324-2336   ryanb@cityofclovis.com
Construction Phase
Clovis Mike Harrison (559) 324-2365   mikeh@cityofclovis.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$315 $-0 $315
Non-bond Funding
Local**
$545 $0 $545
 
Total**** $860 $-0 $860

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$70 $0 $70 $70 $70 $0
Right of Way
$60 $0 $60 $60 $60 $0
Construction
$730 $-0 $729 $651 $651 $78
 
Total* $860 $-0 $860 $782 $782 $78

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/12/2010 

07/12/2010 
 

 
07/12/2010 

07/12/2010 
100  07/12/2010 

07/12/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2010 

11/30/2010 
 

03/01/2011 
11/01/2010 

05/01/2011 
100  11/01/2010 

03/01/2011 


Begin Right of Way Phase

End Right of Way Phase
01/01/2011 

01/31/2011 
 

03/01/2011 
01/01/2011 

05/01/2011 
100  01/15/2011 

03/01/2011 


Begin Construction Phase

End Construction Phase
06/01/2011 

09/01/2011 
03/01/2011 

03/01/2011 
08/01/2011 

12/01/2011 
100  08/01/2012 

01/22/2013 
-12 

-14 
Begin Closeout Phase

End Closeout Phase
10/01/2011 

11/01/2011 
03/01/2011 

 
12/01/2011 

02/01/2012 
100  01/22/2013 

03/08/2013 
-14 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in System Reliability
Increase in Throughput
Lane Miles Added (Mixed)
Pavement Lane Miles
Peak Period Time Savings (minutes)
Reduced Emissions
Reduced Operating/Maintenance Cost
Rehabilitated Lane Miles (miles)
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$315,385
Current Approved:
$315,000
Actual Expenditures:
$315,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle