Caltrans Logo

12TH AVE WIDENING FROM GRANGEVILLE TO FARGO

Description: 12TH AVE WIDENING FROM GRANGEVILLE TO FARGO

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings County
City Hanford
Zip Code 93230
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Lane Miles Added (HOV)  2      
Lane Miles Added (Mixed)        
Rehabilitated Lane Miles (miles)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Hanford Lou Camara (559) 585-2567   lcamara@ci.hanford.ca.us
Design (PS&E) Phase
Hanford Lou Camara (559) 585-2567   lcamara@ci.hanford.ca.us
Right of Way Phase
Hanford Lou Camara (559) 585-2567   lcamara@ci.hanford.ca.us
Construction Phase
Hanford Lou Camara (559) 585-2567   lcamara@ci.hanford.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$750 $0 $750
Non-bond Funding
Local**
$2,390 $0 $2,390
 
Total**** $3,140 $0 $3,140

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$20 $0 $20 $20 $20 $0
Design(PS&E)
$125 $0 $125 $125 $125 $0
Right of Way
$200 $0 $200 $487 $487 $-287
Construction
$2,795 $0 $2,795 $2,679 $2,679 $116
 
Total* $3,140 $0 $3,140 $3,310 $3,310 $-170

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2010 

12/01/2010 
03/01/2011 

03/01/2011 
11/01/2010 

06/06/2011 
100  11/01/2010 

05/01/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2010 

10/01/2010 
03/01/2011 

03/01/2011 
02/01/2011 

01/02/2012 
100  02/01/2011 

10/30/2011 


Begin Right of Way Phase

End Right of Way Phase
01/01/2011 

05/01/2011 
03/01/2011 

03/01/2011 
03/02/2011 

10/03/2011 
100  03/02/2011 

03/30/2012 


-6 
Begin Construction Phase

End Construction Phase
08/01/2011 

12/01/2011 
03/01/2011 

03/01/2011 
03/05/2011 

08/06/2012 
100  07/30/2012 

02/28/2013 
-17 

-7 
Begin Closeout Phase

End Closeout Phase
12/15/2011 

01/01/2012 
03/01/2011 

 
08/06/2012 

10/29/2012 
100  03/01/2013 

09/26/2013 
-7 

-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Lane Miles Added (HOV) 2
Lane Miles Added (Mixed)
Rehabilitated Lane Miles (miles) 2

Bond Funding Cost
Adopted:
$750,000
Current Approved:
$750,000
Actual Expenditures:
$750,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle