Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
12TH AVE WIDENING FROM GRANGEVILLE TO FARGO |
Description: 12TH AVE WIDENING FROM GRANGEVILLE TO FARGO
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings County |
City | Hanford |
Zip Code | 93230 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | ||
Rehabilitated Lane Miles (miles) | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Design (PS&E) Phase |
Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Right of Way Phase |
Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Construction Phase |
Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$750 | $0 | $750 | ||||
Non-bond Funding | |||||||
Local** |
$2,390 | $0 | $2,390 | ||||
Total**** | $3,140 | $0 | $3,140 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$20 | $0 | $20 | $20 | $20 | $0 | |
Design(PS&E) |
$125 | $0 | $125 | $125 | $125 | $0 | |
Right of Way |
$200 | $0 | $200 | $487 | $487 | $-287 | |
Construction |
$2,795 | $0 | $2,795 | $2,679 | $2,679 | $116 | |
Total* | $3,140 | $0 | $3,140 | $3,310 | $3,310 | $-170 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2010 12/01/2010 |
03/01/2011 03/01/2011 |
11/01/2010 06/06/2011 |
100 | 11/01/2010 05/01/2011 |
0 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2010 10/01/2010 |
03/01/2011 03/01/2011 |
02/01/2011 01/02/2012 |
100 | 02/01/2011 10/30/2011 |
0 2 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2011 05/01/2011 |
03/01/2011 03/01/2011 |
03/02/2011 10/03/2011 |
100 | 03/02/2011 03/30/2012 |
0 -6 |
Begin Construction Phase
End Construction Phase |
08/01/2011 12/01/2011 |
03/01/2011 03/01/2011 |
03/05/2011 08/06/2012 |
100 | 07/30/2012 02/28/2013 |
-17 -7 |
Begin Closeout Phase
End Closeout Phase |
12/15/2011 01/01/2012 |
03/01/2011 |
08/06/2012 10/29/2012 |
100 | 03/01/2013 09/26/2013 |
-7 -11 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | ||
Rehabilitated Lane Miles (miles) | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$750,000 |
Current Approved: |
$750,000 |
Actual Expenditures: |
$750,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle