LOS CARNEROS/CALLE ROUNDABOUT

Description: Los Carneros/Calle Roundabout

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara County
City Goleta
Zip Code 93117
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Goleta Rosemarie Gaglione (805) 961-7569   rgaglione@cityofgoleta.org
Design (PS&E) Phase
Goleta Rosemarie Gaglione (805) 961-7569   rgaglione@cityofgoleta.org
Right of Way Phase
Goleta Rosemarie Gaglione (805) 961-7569   rgaglione@cityofgoleta.org
Construction Phase
Goleta Rosemarie Gaglione (805) 961-7569   rgaglione@cityofgoleta.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$335 $0 $335
Non-bond Funding
Local**
$432 $0 $432
 
Total**** $767 $0 $767

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$10 $0 $10 $10 $10 $0
Design(PS&E)
$75 $0 $75 $275 $275 $-200
Right of Way
$12 $0 $12 $27 $27 $-15
Construction
$670 $0 $670 $1,319 $1,319 $-649
 
Total* $767 $0 $767 $1,632 $1,632 $-865

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/15/2010 

09/15/2010 
 

 
09/15/2010 

09/15/2010 
100  09/15/2010 

09/15/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2010 

02/20/2011 
12/19/2013 

12/19/2013 
08/16/2011 

03/31/2012 
100  09/30/2010 

01/31/2012 
11 

Begin Right of Way Phase

End Right of Way Phase
09/15/2010 

11/01/2010 
12/19/2013 

12/19/2013 
05/27/2011 

07/15/2011 
100  05/27/2011 

01/31/2012 


-7 
Begin Construction Phase

End Construction Phase
05/01/2011 

07/30/2011 
12/19/2013 

12/19/2013 
04/17/2012 

01/04/2013 
100  03/01/2012 

11/15/2013 


-10 
Begin Closeout Phase

End Closeout Phase
08/05/2011 

09/30/2011 
12/19/2013 

 
01/04/2013 

08/14/2013 
100  02/04/2014 

04/30/2014 
-13 

-9 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$335,000
Current Approved:
$335,000
Actual Expenditures:
$335,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle