Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
PARSONS AVE ADA GIVENS GAP |
Description: Parsons Ave Ada Givens Gap
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced County |
City | Merced |
Zip Code | |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Reduced Emissions |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Merced | Josh Ewen | (209) 385-6827 | ewej@cityofmerced.org | |
Design (PS&E) Phase |
Merced | Daryl Jordan | (209) 385-6846 | jordanj@cityofmerced.org | |
Right of Way Phase |
Merced | Josh Ewen | (209) 385-6827 | ewenj@cityofmerced.org | |
Construction Phase |
Merced | Ken Elwin | (209) 385-6846 | elwink@cityofmerced.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$500 | $-100 | $400 | ||||
Non-bond Funding | |||||||
Local** |
$1,250 | $0 | $1,250 | ||||
Total**** | $1,750 | $-100 | $1,650 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $20 | $20 | $80 | |
Right of Way |
$750 | $0 | $750 | $429 | $429 | $321 | |
Construction |
$900 | $-100 | $800 | $825 | $825 | $-25 | |
Total* | $1,750 | $-100 | $1,650 | $1,273 | $1,273 | $377 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2009 10/01/2009 |
03/01/2011 |
10/01/2009 03/31/2011 |
100 | 10/01/2009 03/31/2011 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2010 12/01/2010 |
03/01/2011 |
05/01/2010 06/30/2011 |
100 | 05/01/2010 12/31/2011 |
0 -6 |
Begin Right of Way Phase
End Right of Way Phase |
02/01/2005 10/01/2010 |
|
02/01/2005 06/02/2006 |
100 | 07/01/2005 06/02/2006 |
-5 0 |
Begin Construction Phase
End Construction Phase |
02/01/2011 06/01/2011 |
03/01/2011 03/01/2011 |
09/01/2011 01/01/2012 |
100 | 05/01/2012 11/17/2012 |
-8 -11 |
Begin Closeout Phase
End Closeout Phase |
07/01/2011 08/01/2011 |
03/01/2011 |
02/01/2012 03/01/2012 |
100 | 11/17/2012 04/02/2013 |
-10 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Reduced Emissions |
Bond Funding Cost | |
---|---|
Adopted: |
$500,000 |
Current Approved: |
$400,000 |
Actual Expenditures: |
$400,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle