Caltrans Logo

PARSONS AVE ADA GIVENS GAP

Description: Parsons Ave Ada Givens Gap

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced County
City Merced
Zip Code
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Merced Josh Ewen (209) 385-6827   ewej@cityofmerced.org
Design (PS&E) Phase
Merced Daryl Jordan (209) 385-6846   jordanj@cityofmerced.org
Right of Way Phase
Merced Josh Ewen (209) 385-6827   ewenj@cityofmerced.org
Construction Phase
Merced Ken Elwin (209) 385-6846   elwink@cityofmerced.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$500 $-100 $400
Non-bond Funding
Local**
$1,250 $0 $1,250
 
Total**** $1,750 $-100 $1,650

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $0 $100 $20 $20 $80
Right of Way
$750 $0 $750 $429 $429 $321
Construction
$900 $-100 $800 $825 $825 $-25
 
Total* $1,750 $-100 $1,650 $1,273 $1,273 $377

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2009 

10/01/2009 
 

03/01/2011 
10/01/2009 

03/31/2011 
100  10/01/2009 

03/31/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2010 

12/01/2010 
 

03/01/2011 
05/01/2010 

06/30/2011 
100  05/01/2010 

12/31/2011 


-6 
Begin Right of Way Phase

End Right of Way Phase
02/01/2005 

10/01/2010 
 

 
02/01/2005 

06/02/2006 
100  07/01/2005 

06/02/2006 
-5 

Begin Construction Phase

End Construction Phase
02/01/2011 

06/01/2011 
03/01/2011 

03/01/2011 
09/01/2011 

01/01/2012 
100  05/01/2012 

11/17/2012 
-8 

-11 
Begin Closeout Phase

End Closeout Phase
07/01/2011 

08/01/2011 
03/01/2011 

 
02/01/2012 

03/01/2012 
100  11/17/2012 

04/02/2013 
-10 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Reduced Emissions

Bond Funding Cost
Adopted:
$500,000
Current Approved:
$400,000
Actual Expenditures:
$400,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle